PM - Chapter 5

PM - Chapter 5

University

18 Qs

quiz-placeholder

Similar activities

Earn Value Management Quiz

Earn Value Management Quiz

University

21 Qs

Effective Communication

Effective Communication

University

15 Qs

ETB2003 short quiz

ETB2003 short quiz

University - Professional Development

20 Qs

HPRO4104 Assessment 1 Preperation

HPRO4104 Assessment 1 Preperation

University

22 Qs

Feasibility Study Quiz

Feasibility Study Quiz

11th Grade - University

15 Qs

Unit 1 - Planning and decision-making

Unit 1 - Planning and decision-making

10th Grade - University

14 Qs

Project Management

Project Management

University

21 Qs

Project Management Quiz

Project Management Quiz

University

15 Qs

PM - Chapter 5

PM - Chapter 5

Assessment

Quiz

Business

University

Medium

Created by

Phan Trinh

Used 4+ times

FREE Resource

18 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The document that officially sanctions the project is the:

Project charter

Project plan

Feasibility study

Cost-benefit analysis

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The work breakdown structure “control points” for the management of a project are the:

Milestones

Work packages

Activities

Constraints

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

One of the most common reasons why projects undergo scope changes is:

Poor work breakdown structure

Poorly defined statement of work

Lack of resources

Lack of funding

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following generally cannot be validated using a work breakdown structure?

Schedule control

Cost control

Quality control

Risk management

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

With the work breakdown structure (WBS) shown on the right, the cost of WBS element 1.2.2.0 is:

$20K

$30K

$50K

Cannot be determined

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

With the work breakdown structure (WBS) shown on the right, the cost of WBS element 1.1.1 is:

$12K

$13K

$25K

Cannot be determined

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

With the work breakdown structure (WBS) shown on the right, the cost of the entire program (1.00.00) is:

$25K

$66K

$91K

Cannot be determined

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?