Đề 7 (601-700)

Đề 7 (601-700)

University

100 Qs

quiz-placeholder

Similar activities

Unit 12 - ELT 502

Unit 12 - ELT 502

University - Professional Development

99 Qs

Linux

Linux

University

101 Qs

MID Veterinary Anatomy Laboratory - UNHAS

MID Veterinary Anatomy Laboratory - UNHAS

University

100 Qs

M101 Midterm Exam

M101 Midterm Exam

University

100 Qs

1-100

1-100

University

97 Qs

GEC102 Quiz

GEC102 Quiz

University

100 Qs

CNBR 1-5

CNBR 1-5

University

100 Qs

CHAPTER 28

CHAPTER 28

University

105 Qs

Đề 7 (601-700)

Đề 7 (601-700)

Assessment

Quiz

Specialty

University

Medium

Created by

Hoàng Nam

Used 6+ times

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

100 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Conflict resolution techniques that can be used in the project include:
Withdrawal, compromise, control and coercion
Control, coerce, compromise, withdraw
Confrontation, compromise, compromise, management.
Mediation, confrontation, coercion and withdrawal.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Long-standing problems have begun to involve and affect many people, thereby creating many dependencies. How should the project manager best handle this situation?
Give it to higher management.
Separate the problem into logical sub-problems
Set the project schedule baseline
Implement risk management.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You created project charters but they weren't approved. Your manager and his supervisor demand that the project begin immediately. Which of the following is best to do?
Implement a coordinated change control process
Show your manager the impact of unapproved actions.
Focus on completing projects that have project charter signatures
Work on the positives of that criticism

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a meeting with some project stakeholders, the project manager is asked to add work and project scope. The project manager talked about the project before the project charter was signed and he remembered that the project sponsor specifically refused to spend more money on the scope given by the people today. . The BEST thing a project manager should do is:
Tell stakeholders that the scope cannot be added anymore
Let the sponsor know about the requirements of stakeholders (related people)
Evaluate the impact of expanding scope
Add tasks as time allows in the project schedule

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are a PM for a project to build a new factory, which you have never done before. The estimated project cost is $30,000,000 and there can be 3 people investing in it. Once started, the project cannot be canceled, there will be large costs of plant and equipment. As PM, you must be careful ?
Consider all cost proposals from the investment
Check your contingency budget
Complete project charter
Carry out risk identification

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A PM manages a fixed price contract. She thinks this is a big customer - changing requirements could affect the project schedule. What should she do first?
Meet stakeholders
Meet the team
Negotiate the remaining parts of the contract
Monitor the change control system

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

All of the following are within the project scope baseline except:
Project scope management plan
Project scope statement
WBS
WBS dictionary

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?