1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What type of Insurance covers severe weather damage?
Public Liability
Builder's Risk
None, Owner will pay damages
None, GC is responsible for severe weather damage.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A worker's strike not cause by GC or subcontractor is a(n)
Excusable delay
Compensable delay
Excusable and compensable delay
None of the alternatives
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If GC was denied a extended time claim and need to still finish on time, they will do this type of acceleration.
Constructive Acceleration
Voluntary Accelaration
Project Driven Accelaration
Directed Acceleration
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Statute of Repose starts when:
The project is finished and owner takes possession of the building.
When the alleged harm happens
when the injured person reports the damage.
When warranties expire.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A contractor commits a material breach when:
Do not submit payment applications on time.
Do not provide sufficient labor and equipment.
Is behind schedule by 5 working days.
Do not attend OAC meetings.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Statute of Repose is the same as Statute of Limitations
Yes
No
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which method is not legally binding
Mediation
Arbitration
Litigation
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?