1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the role of a quantity surveyor during the pre-construction period?
Preliminary estimates of the project
Valuation of variation
Preparation of final account
Development of building concepts
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of a bill of quantities?
Helps in cost analysis and cost planning
Helps in selecting competitive bidders
Helps in preparation of final payment certificates
Helps in developing building concepts
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the maximum percentage of retention money in large contracts?
5%
8%
10%
2%
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of an interim payment certificate?
To commission the project
To prepare the final account
To enable the contractor to get paid for work done during the project time
To release the final payment to the contractor
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the method commonly used for preparing payment certificates?
By estimation
Stage by stage
Minimum payment
By calendar
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of approximate estimation in construction?
To produce a focus of the possible or probable cost of a project before the building is designed in detail
To determine the exact cost of a project after the building is completed
To compare the cost of different construction materials
To calculate the cost of labor for a construction project
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What factors should be considered when choosing the method of approximate estimating to use?
Information available, available time, degree of accuracy, experience of the estimator
Type of soil, form of construction, circulation space, maintenance services
Site location, market conditions, tendering procedures, financial conditions
Size of the structure, plan shape, wall/floor area ratio, storey height/overall heights
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?