1.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
What is the purpose of appointing a quantity surveyor to produce a bill of quantities (BOQ)?
To reduce transparency in the tender process
To complicate the tender process
To save money on the contract price
To increase the contract price
2.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
What are the two main types of bill of quantities (BOQ) according to NRM2 and RICS?
Firm and flexible
Approximate and accurate
Firm and approximate
Precise and estimated
3.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
How can a bill of quantities (BOQ) help during the tender stage of a project?
By increasing the chances of overpricing by contractors
By allowing contractors to omit necessary elements
By ensuring contractors base their price on an identical list of items
By complicating the negotiation process
4.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
What does a function bill of quantities (BOQ) allow for during the tender process?
Complication of the negotiation process
Increased chances of front loading costs by contractors
Opportunity for contractors to omit vital elements
Direct comparison between contractors and their prices
5.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
How can a bill of quantities (BOQ) be beneficial during the construction phase?
By making variations difficult to identify
By helping to save money in case of reduced quantity price
By complicating the regular payments valuation process
By increasing the possibility of client exploitation by the contractor
6.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
What is the purpose of having a bill of quantities (BOQ) during the post-construction phase?
To complicate the asset management process
To decrease transparency in the final accounting process
To make lifecycle estimates and maintenance cost inaccurate
To evaluate final payments at final account stage
7.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
What is the potential benefit of having a bill of quantities (BOQ) for asset management purposes?
It can lead to inaccurate lifecycle estimates
It can complicate the maintenance cost measurement
It can act as a readily available document for asset management purposes
It can decrease transparency in the final accounting process
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?