1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What needs to be done before leaving the work site that involves work performed at a junction pole?
pg.52
Phase check
Amp check
Make sure house meters are on
Voltage check
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be be recorded before starting work on a junction pole where the jumpers will be removed?
pg.52
Where is lunch?
Test phasing sticks
Phase sequence
Rotation at the meter
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What would happen if a normal open switch is not phased correctly and closed?
pg.52
phase to phase fault
nothing
extremely high voltage
Frequency drop
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the name for a high voltage voltmeter used for proving phase sequence?
pg.53
Multimeter
Volt meter
Phasing meter
Rotation meter
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the name of the part of the phasing sticks that does not have the meter attached to it?
pg.53
Meter probe
Insulated jumper
Phasing probe
Capacitive test point
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the first step in the steps taken to prove phase sequence?
pg.54
Test phasing sticks
Verify correct voltage
Confirm proper phasing across open point
Record phase sequence
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the second step in proving phase sequence?
pg. 54
Test phasing sticks
Verify correct voltage on both sides of open point
Confirm proper phase sequence
Record phase sequence
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?