PM - Lesson 6

PM - Lesson 6

University

13 Qs

quiz-placeholder

Similar activities

Listening skills

Listening skills

University

13 Qs

Navigating AI and Cell Phone Use

Navigating AI and Cell Phone Use

10th Grade - University

10 Qs

High Note, unit 5A

High Note, unit 5A

University

15 Qs

Dear Reader: Take the Path: Introduction Quiz

Dear Reader: Take the Path: Introduction Quiz

University

8 Qs

1.09 At the Mall ~ Listening Quizizz

1.09 At the Mall ~ Listening Quizizz

University

10 Qs

Fred Jones Theory of PAT

Fred Jones Theory of PAT

University

10 Qs

Learning Strategies & Learning Autonomy.

Learning Strategies & Learning Autonomy.

University

10 Qs

Sports and Challenges Quiz, GEP-2 V U-2

Sports and Challenges Quiz, GEP-2 V U-2

University

10 Qs

PM - Lesson 6

PM - Lesson 6

Assessment

Quiz

English

University

Easy

Created by

Phan Trinh

Used 1+ times

FREE Resource

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The shortest time necessary to complete all of the activities in a network is called the:

Activity duration length

Critical path

Maximum slack path

Compression path

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following cannot be identified after performing a forward and backward pass?

Dummy activities

Slack time

Critical path activities

How much overtime is scheduled

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not a commonly used technique for schedule compression?

Resource reduction

Reducing scope

Fast-tracking activities

Use of overtime

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A network-based schedule has four paths, namely 7, 8, 9, and 10 weeks. If the 10-week path is compressed to 8 weeks, then:

We now have two critical paths.

The 9-week path is now the critical path.

Only the 7-week path has slack.

Not enough information is provided to make a determination.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The major disadvantage of using bar charts to manage a project is that bar charts:

Do not show dependencies between activities

Are ineffective for projects under one year in length

Are ineffective for projects under $1 million in size

Do not identify start and end dates of a schedule

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The first step in the development of a schedule is a:

Listing of the activities

Determination of dependencies

Calculation of effort

Calculation of durations

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Reducing the peaks and valleys in manpower assignments in order to obtain a relatively smooth manpower curve is called:

Manpower allocation

Manpower leveling

Resource allocation

Resource commitment planning

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?