PSK Quiz-1

PSK Quiz-1

Professional Development

7 Qs

quiz-placeholder

Similar activities

AGILÍZATE

AGILÍZATE

Professional Development

10 Qs

Day 3 Class Quiz

Day 3 Class Quiz

Professional Development

10 Qs

 SAFe POPM 6.0

SAFe POPM 6.0

Professional Development

9 Qs

ATIVIDADE KANBAN

ATIVIDADE KANBAN

Professional Development

5 Qs

Alige course - Week 2 challenges

Alige course - Week 2 challenges

Professional Development

10 Qs

Scrum Master

Scrum Master

Professional Development

10 Qs

Agile Project Management

Agile Project Management

Professional Development

10 Qs

02 Manifiesto Agil - Scrum

02 Manifiesto Agil - Scrum

Professional Development

7 Qs

PSK Quiz-1

PSK Quiz-1

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Mustafa Yıldırım

Used 6+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

  Workflow can be thought of as the Scrum Team's policy for which of the following?
(choose the best answer)

How to get work done.

How to increase the Team's WIP limit.

What completed work looks like.

Defining when development is complete and validation begins.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

True or False: Scrum Events and scrum accountabilities are changed when using Scrum with Kanban. The Scrum Team might choose to omit the Retrospective.

True

False

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

True or False: Reducing WIP limits will always result in decreased productivity.

True

False

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

True or False: When using Scrum with Kanban you can release multiple times during the Sprint.

True

False

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

True or False: The WIP Limit can only be changed during the Sprint Retrospective.

True

False

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

True or False: If Developers use tasks, then their WIP limits should primarily apply to tasks in the Sprint Backlog.

True

False

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Who is accountable for the Definition of Workflow for the Sprint Backlog?
(Choose the best answer)

The Scrum Team.

The Scrum Master.

The Product Owner.

The Developers.