1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A haulage operator transported 470 tonnes of goods in a period over a total distance of 5,600 kilometres (km).Costs incurred in the period totalled $3,579,520.
What was the cost per tonne per km in the period (to two decimal places)?
$________
$1.36
$1.46
$1.37
$1.33
2.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
The following items are in the cost accounts of a business for a period:
The under-absorbed fixed production overheads are to be included in the calculation of gross profit for the period.
What s the gross profit for the period?
$ ____________
$113340
$114450
$225540
$112230
3.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Which TWO of the following are characteristics of continuous data?
They are measured rather than counted
They have a finite number of possible values within a range
They have clear spaces between values
They must be quantitative
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which of the following are features of process costing?
(1) Valuation of closing work in progress
(2) Loss in process due fo wastage
(3) Output from one process becomes the input for the next
1 and 2 only
2 and 3 only
1 and 3 only
2 only
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
The management accountant of a manufacturing business has calculated the following performance indicators using data concerning direct labour hours.
Capacity ratio 83.6%
Efficiency ratio 104.8%
What is the production volume ratio (to one decimal place)?
__________
85.5%
85.6%
87.6%
84.6%
6.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
The standard cost of a product shows :
During a period 600 units were produced and 4,200 hours were worked at a total labour cost of $50,400.
What was the labour rate variance for the period
$9,000 Favourable
$9,000 Adverse
$12,600 Adverse
$12,600 Favourable
7.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
Are the following statements regarding the setting of budgets true or false?
1) Expectations budgets are useful for resource planning
2) Aspirations budgets are useful for motivational purposes
both statements are true
both statements are false
statement 1 is true statement 2 is false
statement 2 is true statement 1 is false
38 questions
Cert 15 - Inventory
Quiz
•
Professional Development
38 questions
CRISC Domain 3 MCQ (A)
Quiz
•
Professional Development
40 questions
Domestic Hot Water 6035-02 | Part 3
Quiz
•
Professional Development
35 questions
Aegis De-escalation
Quiz
•
Professional Development
41 questions
Networking with Windows Server
Quiz
•
Professional Development
40 questions
Domestic Hot Water 6035-02 | Part 4
Quiz
•
Professional Development
40 questions
Quiz_31.03.2023
Quiz
•
Professional Development
35 questions
BR23-(1)-A
Quiz
•
Professional Development
15 questions
Multiplication Facts
Quiz
•
4th Grade
20 questions
Math Review - Grade 6
Quiz
•
6th Grade
20 questions
math review
Quiz
•
4th Grade
5 questions
capitalization in sentences
Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance
Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions
Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines
Quiz
•
Professional Development
12 questions
Dividing Fractions
Quiz
•
6th Grade