BCS_IT Project Management Foundation

BCS_IT Project Management Foundation

Professional Development

20 Qs

quiz-placeholder

Similar activities

Indicators 1

Indicators 1

Professional Development

18 Qs

IOC Day 2 (Module 1-4)

IOC Day 2 (Module 1-4)

Professional Development

20 Qs

Product Quiz

Product Quiz

Professional Development

15 Qs

CPR_Quiz_Arrays and strings

CPR_Quiz_Arrays and strings

Professional Development

20 Qs

Unit4_MS_Magnetic Materials

Unit4_MS_Magnetic Materials

Professional Development

20 Qs

DTA Kaun Banega QuizPati - Theme: General Knowledge

DTA Kaun Banega QuizPati - Theme: General Knowledge

Professional Development

20 Qs

Managing Spills (Procedures)

Managing Spills (Procedures)

Professional Development

19 Qs

WS Area Jawa Bali 2020

WS Area Jawa Bali 2020

Professional Development

20 Qs

BCS_IT Project Management Foundation

BCS_IT Project Management Foundation

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Priyadarshi Saha

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the primary goal of project management?
Generating revenue
Delivering projects on time and within budget
Maximizing individual team recognition
Expanding the company's physical infrastructure

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which document formally authorizes the initiation of a project?
Project schedule
Risk assessment
Stakeholder analysis
Project charter

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does the critical path represent in a project schedule?
The most difficult tasks
The path with the least amount of activities
The longest sequence of dependent tasks
The tasks assigned to the most skilled team members

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the purpose of a Gantt chart in project management?
Identifying risks
Managing budgets
Visualizing project schedule
Tracking team performance

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the term for a document that defines the specific work to be done in a project?
Stakeholder analysis
Project Charter
Scope statement
Gantt chart

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which project management constraint is often referred to as the 'triple constraint'?
Scope, risk, and quality

Scope,Time and cost

Risk, resources, and scope
Stakeholders, time, and budget

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is a risk register in project management?
A document listing team members' names
A record of identified risks and their characteristics
A list of tasks in the project schedule
A log of completed project milestones

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?

Discover more resources for Professional Development