PMP SET 1.6.Quality

PMP SET 1.6.Quality

Professional Development

15 Qs

quiz-placeholder

Similar activities

LIFE 20 August 2022

LIFE 20 August 2022

Professional Development

20 Qs

Lean Six Sigma Green Belt Exam - DEFINE

Lean Six Sigma Green Belt Exam - DEFINE

Professional Development

15 Qs

PMP R3 P2

PMP R3 P2

Professional Development

10 Qs

Contributing to the delivery of a project

Contributing to the delivery of a project

Professional Development

12 Qs

PMP PROJECT QUALITY MANAGEMENT

PMP PROJECT QUALITY MANAGEMENT

Professional Development

10 Qs

PM Skills for Life Training

PM Skills for Life Training

Professional Development

15 Qs

Midterm Exam

Midterm Exam

Professional Development

14 Qs

Project Controls warm up

Project Controls warm up

Professional Development

12 Qs

PMP SET 1.6.Quality

PMP SET 1.6.Quality

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Ibu Alisya

Used 2+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. The line in the middle of a control chart is called the:
A. Rule of seven
B. Mean
C. Control limit
D. Specification limit

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

2. A project manager is using a cause-and-effect diagram with the team to determine how various factors might be linked to potential problems. In which step of the quality management process is the project manager involved in?
A. Manage quality
B. Plan quality management
C. Control quality
D. Quality troubleshooting

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

3. During project execution, a new version of a standard is issued. The project team meets with the quality department to determine how this updated standard will be applied to the current project. Which part of the quality process is this under?
A. Manage quality
B. Plan quality
C. Perform quality control
D. Value engineering

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

4. Which of the following BEST describes the results of an increase in quality?
A. Increased productivity, increased cost effectiveness, and increased cost risk
B. Increased productivity, decreased cost effectiveness, and increased cost risk
C. Increased productivity, increased cost effectiveness, and decreased cost risk
D. Increased productivity, decreased cost effectiveness, and decreased cost risk

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

5. The project has had a major defect and the project manager has gotten the project team and the process engineers involved in analyzing the situation. Two groups disagree where the fault lies. One of the groups says that the real fault is the age of the equipment. Another says it is the lack of a material for the correct quality. The project manager decides to use a fishbone diagram to help the process. Which of the following would BEST describe what the group is involved in?
A. manage quality
B. marginal analysis
C. control quality
D. quality analysis

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

6. All of the following are quality planning tools and techniques except ___
A. Cost-benefit analysis
B. Design of experiment
C. Cost of quality (COQ)
D. Quality audit

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

7. The actual testing results for the new computer virtualization project have arrived from the seller. The results indicate the project is not meeting the overall quality requirements. If the project manager meets with team members to analyze the problem, the project manager is involved in:
A. Manage Quality
B. Quality planning
C. Quality control
D. Quality management

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?