1 - Introducing SCRUM in SAFe
Quiz
•
Computers
•
Professional Development
•
Practice Problem
•
Hard
Claudia Lidia
Used 7+ times
FREE Resource
Enhance your content in a minute
10 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Select which is an agile framework:
Kanban
Continuous Integration
SAFe
Scrum
Test-driven development
Answer explanation
Agile frameworks:
SAFe, Scrum, Kanban
Practices:
Continuous Integration
Test-driven development
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
_______________ over processes and tools.
responding to change
comprehensive documentation
individuals and interactions
contract negotiations
Answer explanation
Individuals and interactions over processes and tools
Working software over comprehensive documentation
Customer collaboration over contract negotiation
Responding to change over following a plan
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Why apply Scrum?
for ‘relay race’ approach to product development
for maximum speed and flexibility
for traditional sequential approach
for fastest customer project output
Answer explanation
“The traditional sequential or ‘relay race’ approach to product development… may conflict with the goals of maximum speed and flexibility. Instead, a holistic or ‘rugby’ approach—where a team tries to go the distance as a unit, passing the ball back and forth—may better serve today’s competitive requirements.”
—Hirotaka Takeuchi and Ikujiro Nonaka, The New New Product Development Game
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
What are the three pillars of Scrum?
adaptation
transparency
inspection
planning
Answer explanation
The three pillars of Scrum — transparency, inspection, and
adaptation — support the Scrum Values.
Values are:
Courage
Commitment
Focus
Respect
Openness
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
That is the terminology for "Daily Scrum" in SAFe?
Team Synch
Daily Stand-up
Team Daily Synch
DSU
Answer explanation
Daily Scrum = Team Synch
6.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Select the statements that are TRUE for 'team backlog':
Team backlog is created by the Agile Team.
Work sizes in the team backlog may be estimated, but estimates do not imply committed delivery.
Team backlog is owned and prioritized by the Product Owner.
The team backlog represents opportunities, not commitments.
Answer explanation
7.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
“Before we build cars, we build people.” — from The Toyota Way
Select which are the SAFe Core Values:
Transparency
Respect for People
Relentless Improvement
Alignment
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
10 questions
Microsoft Teams
Quiz
•
Professional Development
10 questions
Software_Sistemas_Operativos
Quiz
•
Professional Development
10 questions
Computing Systems
Quiz
•
9th Grade - Professio...
15 questions
QUIZ HSE TownHall Meeting Desember 2021
Quiz
•
Professional Development
10 questions
Minigame 2-HB Academy
Quiz
•
Professional Development
14 questions
Intro to Statistics for ML
Quiz
•
Professional Development
10 questions
PUBG
Quiz
•
3rd Grade - Professio...
15 questions
R&D Days
Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Honoring the Significance of Veterans Day
Interactive video
•
6th - 10th Grade
9 questions
FOREST Community of Caring
Lesson
•
1st - 5th Grade
10 questions
Exploring Veterans Day: Facts and Celebrations for Kids
Interactive video
•
6th - 10th Grade
19 questions
Veterans Day
Quiz
•
5th Grade
14 questions
General Technology Use Quiz
Quiz
•
8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Circuits, Light Energy, and Forces
Quiz
•
5th Grade
19 questions
Thanksgiving Trivia
Quiz
•
6th Grade