1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A Project Manager should ____ when dealing with High Power and High Interest Stakeholders:

Keep satisfied

Keep informed

Engage closely

Minimal effort

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The major disadvantage of using Bar Charts to manage a project is that Bar Charts:

Do not show dependencies between activities

Are ineffective for projects under one year in length

Are ineffective for projects under $ 1 million in size

Do not identify start and end dates of a schedule

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The following statements are the potential benefits of a PMO, EXCEPT:

Improved reliability of the information provided

Better project prioritization

Manage resource allocation

Increased visibility of project progress

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are working on a new product development that requires review and approval from a regulatory body. Which of the following describe the type of dependencies in your project?

Mandatory

Discretionary

Internal

External

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

One of the most common reasons why projects undergo scope changes is:

Poor Work Breakdown Structure (WBS)

Poorly defined Statement of Work

Lack of resources

Lack of funding

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The following techniques for schedule compression does not incur additional costs, EXCEPT:

Resource leveling

Crashing

Doing series work in parallel

All of the above or none of the above

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During a project team meeting, a team member suggested an enhancement to the scope that is beyond the scope of the project charter. The project manager points out that the team needs to concentrate on completing all the work required. This is an example of:

Change management

Stakeholder engagement

Product enhancement

Scope management

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?