Lecture 8 end of lesson

Lecture 8 end of lesson

9th - 12th Grade

10 Qs

quiz-placeholder

Similar activities

Time and project management

Time and project management

12th Grade

14 Qs

Round 2

Round 2

KG - Professional Development

10 Qs

PMIPCC Gyan Lahari 2024

PMIPCC Gyan Lahari 2024

12th Grade

10 Qs

iMovie & Google Draw

iMovie & Google Draw

4th Grade - Professional Development

10 Qs

Project Size Estimation Techniques Quiz

Project Size Estimation Techniques Quiz

12th Grade

15 Qs

ICT in education

ICT in education

1st Grade - Professional Development

10 Qs

What type of attitude is this?

What type of attitude is this?

11th - 12th Grade

10 Qs

Identifying  Project Resources

Identifying Project Resources

9th Grade

10 Qs

Lecture 8 end of lesson

Lecture 8 end of lesson

Assessment

Quiz

Professional Development

9th - 12th Grade

Hard

Created by

Silviu Acaru

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a work breakdown structure (WBS)?

A visual representation of the project schedule

A list of all the tasks required to complete the project

A document that outlines the project budget

A tool used to track project progress

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which estimating technique uses statistical data to estimate project costs?

Parametric estimating

Historical estimating

Three-point estimating

PERT estimating

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the formula for three-point estimating?

(Optimistic + Pessimistic + Most Likely)/3

(Optimistic + Pessimistic)/2

(Most Likely + Pessimistic)/2

(Optimistic + 4 x Most Likely + Pessimistic)/6

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which estimating technique involves the project team providing estimates anonymously and then coming to a consensus on the final estimate?

Parametric estimating

Historical estimating

Three-point estimating

Wideband Delphi estimating

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a network diagram?

A visual representation of the project schedule

A document that outlines the project budget

A tool used to track project progress

A chart that shows the relationship between project tasks

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which scheduling tool is commonly used to show the start and end dates for project tasks?

Network diagram

Gantt chart

Project calendar

Milestones

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a Gantt chart?

A visual representation of the project schedule

A document that outlines the project budget

A tool used to track project progress

A chart that shows the relationship between project tasks

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?