CMA 490 - Chapter 3 Review

CMA 490 - Chapter 3 Review

University

27 Qs

quiz-placeholder

Similar activities

ABT Midterm Exam

ABT Midterm Exam

University

30 Qs

Quiz Review

Quiz Review

2nd Grade - University

25 Qs

English word meaning

English word meaning

KG - Professional Development

22 Qs

BUILTECH1 FINAL EXAM

BUILTECH1 FINAL EXAM

University

25 Qs

Lighting - Types of Lamps

Lighting - Types of Lamps

University

30 Qs

Session 2

Session 2

2nd Grade - University

24 Qs

untitled

untitled

3rd Grade - University

25 Qs

VDA - Room

VDA - Room

University

31 Qs

CMA 490 - Chapter 3 Review

CMA 490 - Chapter 3 Review

Assessment

Quiz

Architecture

University

Medium

Created by

Jeremiah Arnett

Used 40+ times

FREE Resource

27 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The critical path method (CPM) is a scheduling approach that identifies the ___ path through work activities to complete a project.

fastest

longest

simlest

shortest

Answer explanation

pg. 44

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A ___ activity is a project activity that has zero float and is part of the critical path.

priority

major

critical

hammock

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Most construction professionals prefer to review a project while looking at the ___.

Gantt chart

network diagram

critical path

notice to proceed

Answer explanation

pg. 45

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Gantt chart is a ___ that includes all activity durations as well as start and finish dates.

pictograph

line graph

pie chart

bar chart

Answer explanation

pg. 45

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Most network diagrams used for construction are ___ diagrams.

activity-on-node (AON)

notice-on-node (NON)

activity-on-arrow (AOA)

notice-on-arrow (NOA)

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

___ is the sequencing of project activities in the order they are to be started.

Network logic

Milestone planning

Activity mapping

Hierarchical scheduling

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A ___ is an activity that directly follows another activity and has a relationship with or constraint related to that activity.

predecessor

successor

dependent

hammock

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?