CMA 490 - Chapter 3 Review
Authored by Jeremiah Arnett
Architecture
University
Used 41+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
27 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The critical path method (CPM) is a scheduling approach that identifies the ___ path through work activities to complete a project.
fastest
longest
simlest
shortest
Answer explanation
pg. 44
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A ___ activity is a project activity that has zero float and is part of the critical path.
priority
major
critical
hammock
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Most construction professionals prefer to review a project while looking at the ___.
Gantt chart
network diagram
critical path
notice to proceed
Answer explanation
pg. 45
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A Gantt chart is a ___ that includes all activity durations as well as start and finish dates.
pictograph
line graph
pie chart
bar chart
Answer explanation
pg. 45
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Most network diagrams used for construction are ___ diagrams.
activity-on-node (AON)
notice-on-node (NON)
activity-on-arrow (AOA)
notice-on-arrow (NOA)
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
___ is the sequencing of project activities in the order they are to be started.
Network logic
Milestone planning
Activity mapping
Hierarchical scheduling
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A ___ is an activity that directly follows another activity and has a relationship with or constraint related to that activity.
predecessor
successor
dependent
hammock
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?