
PMP - Lesson 5 Support Project Team

Quiz
•
Professional Development
•
Professional Development
•
Medium
Training eNetwoQ ServIT Indonesia
Used 9+ times
FREE Resource
21 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
Which of the following represents a risk?
a. We have determined that our schedule is not going to meet the required deadline
B. Due to a higher inflation rate, it is possible that future commodity prices will be 3 to 7% higher over the next 2 years, thus increasing the cost of the project.
C. There are not enough resources to complete the work on time
D. The change in the prime rate has caused our funding source to be unable to provide the money we need in the upcoming project phase
Answer explanation
Choice B represents a risk as it highlights the uncertainty of future commodity prices due to inflation, which could increase project costs. The other options describe issues already affecting the project rather than potential future risks.
2.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
Which conflict management approach is best suited for a situation where both parties refuse to give in on their position?
A. Compromise/reconcile
B. Accommodate/smooth
C. Withdraw/avoid
D. Force/direct
Answer explanation
The best approach is A. Compromise/reconcile, as it encourages both parties to find a mutually acceptable solution, which is essential when neither side is willing to concede their position.
3.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
Which is true about conflict in projects?
A. Too much conflict reflects poorly on the team.
B. Too much conflict reflects poorly on the project manager.
C. Conflict is inevitable.
D. Conflict is to be addressed only when it disrupts the project
Answer explanation
C. Conflict is inevitable. In projects, differing opinions and interests often arise, making conflict a natural part of team dynamics. Recognizing this helps in managing it effectively rather than avoiding it.
4.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
The product owner is unavailable to decide about a product feature. What is this considered?
A. Work request
B. Impediment
C. Backlog refinement
D. Priority
Answer explanation
The product owner's unavailability to decide on a feature is an impediment, as it hinders progress. An impediment is anything that blocks the team from achieving their goals, making option B the correct choice.
5.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
Which of the following is a technique used by project teams to bring everyone together on a set reoccurring basis to share what may be blocking or impeding their work or plans?
A. Daily standup meeting
B. Iteration review
C. Retrospective
D. Project kickoff
Answer explanation
The Daily standup meeting is a technique where project teams meet regularly to discuss progress and identify any blockers. This fosters communication and helps in addressing issues promptly, making it the correct choice.
6.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
Which of the following is the best example of a blocker?
A. The team cannot decide when to schedule the next iteration review
B. The demonstration is not ready for the iteration review
C. Clearance from another team to use content for the demo won’t be ready within the current iteration
D. The demonstration fails in front of the product owner during the iteration review
Answer explanation
Choice C is the best example of a blocker because it indicates a dependency on another team that prevents progress within the current iteration, directly impacting the ability to complete the demo.
7.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
While you are working on a SWOT analysis for a risk response, a team member asks you to show them how it’s done. Which type of coaching is this?
A. Informal
B. Formal
C. Scheduled
D. Timeboxed
Answer explanation
The coaching requested is informal because it occurs spontaneously during work, rather than being part of a structured or scheduled training session.
Create a free account and access millions of resources
Similar Resources on Wayground
19 questions
Bayer PH BRAVE R2 Go-live Celebration

Quiz
•
Professional Development
18 questions
Rerrange the sentences

Quiz
•
9th Grade - Professio...
18 questions
Recap Kursus Change Management

Quiz
•
Professional Development
18 questions
Change Management & Project Management PELINDO

Quiz
•
Professional Development
18 questions
Personal Effectiveness Workshop 2 Recap

Quiz
•
Professional Development
16 questions
Stakeholder Management PMP

Quiz
•
Professional Development
20 questions
Communication

Quiz
•
Professional Development
21 questions
G00813 - Basics - ENG

Quiz
•
Professional Development
Popular Resources on Wayground
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
10 questions
Ice Breaker Trivia: Food from Around the World

Quiz
•
3rd - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
20 questions
ELA Advisory Review

Quiz
•
7th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Multiplication and Division Unknowns

Quiz
•
3rd Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade