PMP - Lesson 6 Close the Project Phase

Quiz
•
Professional Development
•
Professional Development
•
Medium
Training eNetwoQ ServIT Indonesia
Used 8+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
Last year, your company released a new service based on a project you managed. The company wants to determine if the new service has increased customer satisfaction. Which tool measures the happiness of users based on their willingness to encourage others to use your service against those who would discourage others to use your service?
A. Net promoter score
B. Net value
C. AB testing
D. Planned value
Answer explanation
The Net Promoter Score (NPS) measures customer satisfaction by assessing the likelihood of users recommending the service to others. It distinguishes between promoters and detractors, making it the correct choice for evaluating user happiness.
2.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
What is the difference between a lessons learned register and a lessons learned repository?
A. The two terms mean the same thing
B. The register applies to a single project, and the repository applies to many projects
C. The repository applies to a single project, and the register applies to many projects.
D. The register contains only areas that need improvement in future projects, and the repository contains areas of improvement as well as positive findings.
Answer explanation
The correct choice is B. A lessons learned register is specific to a single project, documenting insights from that project, while a lessons learned repository aggregates insights from multiple projects for broader learning.
3.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
n which of the following situations would you not perform the Close Project or Phase process?
A. When a project is terminated
B. When a project phase is complete
C. When a customer validates interim deliverables
D. When a project is complete
Answer explanation
You would not perform the Close Project or Phase process when a customer validates interim deliverables (C), as this indicates ongoing work rather than completion of a project or phase.
4.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
If a project was terminated early, why would the project manager insist that the team perform the Close Project or Phase process?
A. To document the reasons why the project was terminated early, and determine how to transfer the finished and unfinished deliverables to others
B. To document that the project was a waste of time and the project and its output are no longer needed
C. To make sure everyone knows that the reason for the project termination was either the team’s or the project manager’s fault
D. To document lessons learned so mistakes won’t be repeated in future project
Answer explanation
The project manager insists on performing the Close Project process to document the reasons for early termination and to manage the transfer of both finished and unfinished deliverables, ensuring proper closure.
5.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
The project manager wants to make sure all team members understand the importance of the whole closing process and asks if there are any more questions. One team member asks, “What would happen if this process was not done?” How should the project manager answer that question?
A. The customer would not be obliged to pay for the project
B. The next related activity, phase, or project might not be authorized to begin.
C. The stakeholders would not have any faith in the project team for future projects.
D. The team members would not be allowed to be assigned to future projects.
Answer explanation
If the closing process is not completed, it can prevent the authorization of subsequent activities or projects, as proper closure ensures all aspects are finalized and documented, which is crucial for moving forward.
6.
MULTIPLE SELECT QUESTION
5 mins • 1 pt
Which three of the following are purposes of the benefits management plan? (Choose three)
A. The benefits identified in the benefits management plan will help guide the measurement of the benefits after implementation
B. The benefits owner will use or may change some of the metrics identified in the benefits management plan to track the actual benefits realized.
C. The benefits owner will ensure that the measurement metrics and methods will be established, tracked, and monitored after implementation
D. The project manager is responsible for tracking the benefits from the project for the time specified in the benefits management plan
Answer explanation
The benefits management plan serves to guide benefit measurement (A), allows the benefits owner to adjust metrics (B), and ensures tracking and monitoring of metrics post-implementation (C). D is incorrect as the project manager's role is different.
7.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
Often the benefits management plan is created before the project is approved along with the business case document. Why is the benefits management plan created?
A. The benefits management plan is a feasibility study used to justify the project
B. The benefits management plan is created to define the methods for creating, tracking, and sustaining the benefits provided by the project.
C. The benefits management plan describes how the project will be planned, managed, controlled
D. The benefits management plan is created by the project sponsor and authorizes the project manager to start the project
Answer explanation
The benefits management plan is created to define the methods for creating, tracking, and sustaining the benefits provided by the project, ensuring that the project's value is realized and maintained over time.
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
WT for AOII

Quiz
•
Professional Development
10 questions
Practice Exam 2 Part 2

Quiz
•
Professional Development
15 questions
Kuis 1 Project Administration

Quiz
•
Professional Development
10 questions
Communication 10 soal (Chapter 10)

Quiz
•
Professional Development
10 questions
Quiz Lesson 3 - Topic F (Risks)

Quiz
•
Professional Development
10 questions
Quiz Lesson 3 - Topic D (Resources and Procurement)

Quiz
•
Professional Development
10 questions
IT Project Management - IT Project Planning

Quiz
•
Professional Development
10 questions
Quiz Project Scope and Deliverables

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
15 questions
Core 4 of Customer Service - Student Edition

Quiz
•
6th - 8th Grade
15 questions
What is Bullying?- Bullying Lesson Series 6-12

Lesson
•
11th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade