CAPM Quiz 1

CAPM Quiz 1

12th Grade

9 Qs

quiz-placeholder

Similar activities

SDLC - Knowledge Check

SDLC - Knowledge Check

11th - 12th Grade

8 Qs

X.5_Project 2_SMANSA

X.5_Project 2_SMANSA

9th - 12th Grade

10 Qs

Curriculum & Frameworks

Curriculum & Frameworks

KG - Professional Development

9 Qs

Amendment of Bylaws - PPTQ Sec 57

Amendment of Bylaws - PPTQ Sec 57

12th Grade

9 Qs

Internet como herramienta educativa

Internet como herramienta educativa

6th Grade - University

7 Qs

Engaging with Digital Learning Tools

Engaging with Digital Learning Tools

12th Grade

10 Qs

Pretest CANVA

Pretest CANVA

10th - 12th Grade

10 Qs

Introduction to Media and Information Literacy

Introduction to Media and Information Literacy

12th Grade

10 Qs

CAPM Quiz 1

CAPM Quiz 1

Assessment

Quiz

Instructional Technology

12th Grade

Medium

Created by

M T

Used 13+ times

FREE Resource

9 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

15 of the 150 questions on the CAPM exam are not graded.

True

False

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many project management knowledge areas are covered in the PMBOK?

8

9

10

11

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many processes do the knowledge areas contain?

39

45

49

53

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of these should NOT be listed as a PM Life Cycle phase?

Initiating

Planning

Execution

Testing

Closing

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A program is a group of related projects managed in a coordinated way

True

False

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A collection of programs & projects managed together to facilitate the attainment of strategic business goals is called?

Business Case

Agile Environment

Portfolio

Progressive Elaboration

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

This Project Management Office Type has a consultative role

Directive

Supportive

Controlling

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The main difference between Projects and Operations is that

Projects support core business functions

Projects are ongoing

Projects are temporary

9.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

All 49 Processes must be used in every project

True

False