Project Integration Management Quiz

Quiz
•
Professional Development
•
Professional Development
•
Medium
Michael Myers
Used 5+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a recommended method for controlling change within a project?
Have only the project manager able to initiate change.
Have each change approved or rejected through a formal change control process
Allow each project member ultimate control of changes within their part of the project without a review process
Freeze scope and allow absolutely no changes
Answer explanation
The change control procedure varies from project to project. However, every change request must be processed through a formal change control process.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager calls you in as a consultant to provide input on developing the Project Charter. According to the PMBOK, your contribution to the project could best be termed as:
Professional Consultant
Expert Judgment
Charter Consultant
Expert Consultancy
Answer explanation
Expert Judgment is judgment provided, based on expertise in an application area, a knowledge area, a discipline, an industry, etc. Expert Judgment is available from many sources including consultants.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which process is concerned with providing forecasts to update current cost information?
Monitor and Control Project Work
Project Management Information System
Close Project or Phase
Direct and Manage Project Work
Answer explanation
During the Monitor and Control Project Work process, work performance data is gathered and passed to the controlling processes. The Monitor and Control Project Work process is responsible for keeping track of the all project's measures, including cost.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following would not be considered an Enterprise Environmental Factor during the Develop Project Charter process?
Scope Statement
Organizational infrastructure
Governmental standards
Marketplace conditions
Answer explanation
The scope statement is clearly not an enterprise environmental factor, whereas the other three choices—governmental standards, organizational infrastructure, and marketplace conditions—are enterprise environmental factors.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The Close Project or Phase process is not performed when:
Cancelling projects
Closing projects
Closing project phases
Reactivating projects
Answer explanation
The Close Project or Phase process allows the project manager to close or finish a specific phase of the project.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of these tools and techniques is common to all seven Project Integration Management processes?
Meetings
Data analysis
Data gathering
Expert Judgment
Answer explanation
All seven processes of Project Integration Management use Expert Judgment as a tool and technique.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are beginning a new project. When should you use the Perform Integrated Change Control process?
Throughout the entire project
Only when closing out the project
Only after the project is completely funded
Only after the project scope is clearly defined
Answer explanation
Changes can occur in the project at any time. The Perform Integrated Change Control process is valuable for managing and tracking those changes.
Create a free account and access millions of resources
Similar Resources on Wayground
7 questions
TPACK

Quiz
•
Professional Development
9 questions
Trivia Time!

Quiz
•
Professional Development
10 questions
Project Risk Mgmt Pretest - Astra International

Quiz
•
Professional Development
10 questions
IPMAC_PMP_L08P_Scope Management

Quiz
•
Professional Development
8 questions
Formative check for CiC understanding

Quiz
•
Professional Development
7 questions
Scope Management Process - Assignment

Quiz
•
Professional Development
10 questions
Introduction to Lean & Six Sigma

Quiz
•
Professional Development
5 questions
Perform Integrated Change Control - Assignment

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
15 questions
Core 4 of Customer Service - Student Edition

Quiz
•
6th - 8th Grade
15 questions
What is Bullying?- Bullying Lesson Series 6-12

Lesson
•
11th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade