8 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A budget for 8,000 units of output shows direct materials cost of £17,400 and a direct labour cost of £12,600. Actual output is 9,000 units.
Using a flexed budget which is correct?
direct materials £19,575
direct labour £14,175
direct materials £19,575
direct labour £12,600
direct materials £17,400
direct labour £14,175
direct materials £17,400
direct labour £12,600
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a Fixed cost for a manufacturing business?
Raw materials to make the product
Salaries of maintenance staff
Production workers paid on the basis of work done
Royalties paid to the designer of the product
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the Economic Order Quantity (EOQ) for material XX5?
£1200
144,000 kg
£144,000
1200 kg
Answer explanation
2x7200x20/£2
2880000/£2
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A company pays its production-line employees on a piecework basis, but with a guaranteed rate. How much will R Williams be paid?
£400
£450
£435
£396
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
From the list below, what would be the best basis of apportionment for lighting and heating overheads?
Carrying value of production equipment
Number of employees
Factory floor space
Time spent servicing production equipment
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the budgeted overhead absorption rate for each department if both are heavily automated?
Cutting £9, Assembly £25
Cutting £9, Assembly £75
Cutting £20, Assembly £25
Cutting £20, Assembly £75
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the budgeted overhead absorption rate for each department if both are labour intensive?
Cutting £9, Assembly £25
Cutting £9, Assembly £75
Cutting £20, Assembly £25
Cutting £20, Assembly £75
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
Quiz SH Dev. Batch
Quiz
•
Professional Development
13 questions
USE OF PPT SLIDES
Quiz
•
Professional Development
13 questions
M4_REPÀSUF3
Quiz
•
Professional Development
9 questions
Software Development
Quiz
•
Professional Development
13 questions
HAIR CUTTING VOCABULARY
Quiz
•
Professional Development
10 questions
Pedagogic Games V
Quiz
•
1st Grade - Professio...
13 questions
5.0 Hazardous Materials and Dangerous Goods Classification
Quiz
•
Professional Development
12 questions
PCHE: Module 2
Quiz
•
Professional Development
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
29 questions
Alg. 1 Section 5.1 Coordinate Plane
Quiz
•
9th Grade
22 questions
fractions
Quiz
•
3rd Grade
11 questions
FOREST Effective communication
Lesson
•
KG
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade