iPMAC_PMP_L08P_Schedule Management and Cost Management

iPMAC_PMP_L08P_Schedule Management and Cost Management

Professional Development

10 Qs

quiz-placeholder

Similar activities

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT

Professional Development

10 Qs

Day3_Quiz_NBKR

Day3_Quiz_NBKR

Professional Development

10 Qs

Project Stakeholder Management

Project Stakeholder Management

Professional Development

10 Qs

Project Risk Management 2022

Project Risk Management 2022

Professional Development

10 Qs

LO6 Business Case & Benefits Management

LO6 Business Case & Benefits Management

Professional Development

15 Qs

SV, CV, SPI, CPI - Assignment

SV, CV, SPI, CPI - Assignment

Professional Development

5 Qs

Agile Product/ Project Management Quiz

Agile Product/ Project Management Quiz

Professional Development

12 Qs

AZ-400 | Mod-1 & 2

AZ-400 | Mod-1 & 2

Professional Development

13 Qs

iPMAC_PMP_L08P_Schedule Management and Cost Management

iPMAC_PMP_L08P_Schedule Management and Cost Management

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Giang Vien

Used 5+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are a project manager overseeing the construction of a Baseball Stadium. The activity of laying the Grass Sod has an optimistic estimate of 10 days, pessimistic estimate of 16 days, and most likely estimate of 13 days. What is the duration within which this task must be completed?

10 days to 16 days   

7 days to 19 days   

12 days to 14 days 

11 days to 15 days

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

There are two activities on your schedule, which are: 1) Install server in lab 2) Move server into the data center. However, the second task can’t start until the server has run in the lab for 5 days without failure. This is an example of what?

Fast Track

Lead

Crashing

Lag

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In a Finish to Start relationship between predecessor and successor activities, a project manager decides to schedule a successor activity 5 days before its predecessor is complete. This is accomplished by providing 5 days of:

Lag

Load

Fast-tracking

Lead

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your project schedule shows a 15 month finish, but your customer has just realized there is a regulatory requirement to complete the project by a certain date and insists this project must be finished in 12 months. Which of the following is the best approach?

Tell the customer it can be done, then cut your estimates by 20%.

Cut the scope by 20%, tell the customer the critical path has changed, and resubmit the schedule for review.

Stand your ground. Cutting scope or time will result in an inferior project outcome.

Inform the customer of the impacts, then crash the project.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The Cost Performance Index (CPI) of a project is 0.8 and you have a limited budget. You are planning to procure a product from the supplier. In this situation, you should:

Ask the supplier to supply a product of slightly lower quality, since it will cost less.   

Try innovative means to lower costs.   

Remove non-critical tasks from the project schedule.   

Try to crash the project as shortening the project schedule decreases costs.   

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What are the 2 estimation methods that take the most time and the least time?

Expert judgement, Three point estimate

Analog, Expert judgement

Bottom up, Analog

Analog, Parametric

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project uses rounding of activity estimates data to the nearest $100, uses staff hours as the unit of measure for resources, and has a variance threshold of 10% deviation from the baseline plan. These would be typically documented in the:

Cost management plan

Scope Statement

WBS

Project charter

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?