1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are a project manager overseeing the construction of a Baseball Stadium. The activity of laying the Grass Sod has an optimistic estimate of 10 days, pessimistic estimate of 16 days, and most likely estimate of 13 days. What is the duration within which this task must be completed?
10 days to 16 days
7 days to 19 days
12 days to 14 days
11 days to 15 days
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
There are two activities on your schedule, which are: 1) Install server in lab 2) Move server into the data center. However, the second task can’t start until the server has run in the lab for 5 days without failure. This is an example of what?
Fast Track
Lead
Crashing
Lag
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
In a Finish to Start relationship between predecessor and successor activities, a project manager decides to schedule a successor activity 5 days before its predecessor is complete. This is accomplished by providing 5 days of:
Lag
Load
Fast-tracking
Lead
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your project schedule shows a 15 month finish, but your customer has just realized there is a regulatory requirement to complete the project by a certain date and insists this project must be finished in 12 months. Which of the following is the best approach?
Tell the customer it can be done, then cut your estimates by 20%.
Cut the scope by 20%, tell the customer the critical path has changed, and resubmit the schedule for review.
Stand your ground. Cutting scope or time will result in an inferior project outcome.
Inform the customer of the impacts, then crash the project.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The Cost Performance Index (CPI) of a project is 0.8 and you have a limited budget. You are planning to procure a product from the supplier. In this situation, you should:
Ask the supplier to supply a product of slightly lower quality, since it will cost less.
Try innovative means to lower costs.
Remove non-critical tasks from the project schedule.
Try to crash the project as shortening the project schedule decreases costs.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What are the 2 estimation methods that take the most time and the least time?
Expert judgement, Three point estimate
Analog, Expert judgement
Bottom up, Analog
Analog, Parametric
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project uses rounding of activity estimates data to the nearest $100, uses staff hours as the unit of measure for resources, and has a variance threshold of 10% deviation from the baseline plan. These would be typically documented in the:
Cost management plan
Scope Statement
WBS
Project charter
Create a free account and access millions of resources
Similar Resources on Wayground
11 questions
Practice Exam 2 Part 1

Quiz
•
Professional Development
10 questions
Programming and Planning Quiz

Quiz
•
Professional Development
10 questions
International project management

Quiz
•
Professional Development
6 questions
Schedule Management Processes - Assignment

Quiz
•
Professional Development
13 questions
PMP Exam Preparation Mocktest With Formula

Quiz
•
Professional Development
5 questions
Cost Final Quiz - Assignment

Quiz
•
Professional Development
10 questions
PBP ala KmR

Quiz
•
Professional Development
12 questions
Bid and Tender Management

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Appointment Passes Review

Quiz
•
6th - 8th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
Grammar Review

Quiz
•
6th - 9th Grade