1.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
In which of the following organizations is the project manager role more likely to be filled as a full-time position?
Functional
Matrix
Projectized
All
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following choices most properly reflects matching roles to responsibilities? (This question tests your past course knowledge as well as your concepts that has developed after the completion of Module 1 in this course)
Senior management: Signing the project charter, approving schedule change requests, and naming the project manager.
Project manager: Signing the project charter, approving schedule change requests, and assigning team resources to activities.
Senior management: Communicating the strategic vision, matching portfolio options to the goals, and signing the project charter.
Program manager: Coordinating multiple project dependencies, Communicating the program vision, and assigning project team members to activities.
3.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
Which of the following statements about a project is not true?
A project can involve a single person.
A project must include all unique elements; otherwise, the work is considered ongoing operations.
A project may create a capability to provide a service.
A project may create a result, such as a research document.
4.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
In a matrix organization, more power is given to the
Functional Manager
Project Manager
Project Coordinator
Team members
5.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
What is considered to be the most useful skill for a project manager who works in a matrix environment in order to achieve project goals?
Leadership skill
Influencing
Conflict management skill
Planning skill
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Marco is an investor, and Jon is a project team member. Both have intensive technical background for the project that you are managing. However, recently they have disagreed on the next step to take for the project. They both decide to defer to whoever has the authority to make this decision. Who has the authority to decide which direction should be taken for the project?
Project manager
Stakeholders
The project team
Investors
7.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
A strategy is thought oriented.
True
False
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
15 questions
POSTES MANAJERIAL - INTEGRITAS
Quiz
•
University
17 questions
Ecosystem Services
Quiz
•
University
15 questions
Piaget Review
Quiz
•
10th - 12th Grade
19 questions
redemption quiz in anaphy
Quiz
•
University
20 questions
UAS Dinamika Kelompok
Quiz
•
University
20 questions
SOAL SUMATIF TENGAH SEMSETER 1B.INGGRIS
Quiz
•
6th Grade - University
18 questions
Sara's Revenge
Quiz
•
KG - 12th Grade
15 questions
Taxation - Introduction to Tax
Quiz
•
University
Popular Resources on Wayground
10 questions
Honoring the Significance of Veterans Day
Interactive video
•
6th - 10th Grade
9 questions
FOREST Community of Caring
Lesson
•
1st - 5th Grade
10 questions
Exploring Veterans Day: Facts and Celebrations for Kids
Interactive video
•
6th - 10th Grade
19 questions
Veterans Day
Quiz
•
5th Grade
14 questions
General Technology Use Quiz
Quiz
•
8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Circuits, Light Energy, and Forces
Quiz
•
5th Grade
19 questions
Thanksgiving Trivia
Quiz
•
6th Grade