Which of the following is a responsibility of the Product Owner?

People and Team

Quiz
•
Education
•
Professional Development
•
Easy
Aditya Soman
Used 1+ times
FREE Resource
9 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Determine the appropriate release dates.
Determine the Developers composition necessary for success.
Determine the appropriate solution or approach for the product.
Determine the length of the Sprints.
Answer explanation
Product owner is the voice of customer. He determines the scope and also the release dates of the products.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The CEO asks one of the Developers to add an activity to the current Sprint. What should the Developers do?
Add the activity to the current Sprint and drop an activity of equal size.
Respect the CEO's authority and add the activity to the current Sprint without any adjustments.
Inform the Product Owner so he she can work with the CEO.
Add the activity to the next Sprint.
Answer explanation
The product owner is the only person who takes decision on scope. Therefore he is the person who should work with the CEO.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is true concerning impediments (Hinderances)?
It is the Scrum Master's top priority to remove impediments.
A slow running server is not considered an impediment.
It is the Product Owner's job to remove impediments.
The Developers should not use daily Scrum meetings to report impediments.
Answer explanation
Scrum masters primary responsibility is to remove impediments
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who should define the Definition of Done?
Product Owner
Scrum Master
Product Owner and Scrum Master
Product Owner and Developers
Answer explanation
Product Owner and Developers should agree upon a Definition of Done before the Sprint Starts
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who is primarily responsible for facilitation, when required, in Scrum events?
Scrum Master
Product Owner
Developers
No one
Answer explanation
Scrum Master is responsible for facilitation.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is MOST likely to result if the Product Owner is not available during a Sprint?
The Sprint is abnormally terminated.
The Developers extends the length of the Sprint until the Product Owner returns.
The product increment may not meet expectations.
The Scrum Master assumes the responsibilities of the Product Owner.
Answer explanation
Since PO will not review the product increment, what gets produced, may not exactly be what the PO wants.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The Product Owner manages the Product Backlog. Who is accountable for estimating the effort to complete the Product Backlog items?
The Developers. As a collective, they have a complete view of the work needed to transform PBIs into Increments of product.
The PMO. They have all the history on projects delivered, and this enables the IT department to make delivery commitments.
The Product Owner. The Product Owner is required to commit on delivery to the users and the stakeholders.
The Scrum Master. The Scrum Master is supposed to get the estimates done from the Developers.
Answer explanation
The Developers are responsible for all estimates. The people who will perform the work make the final estimate.
8.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During an Sprint planning session, three Scrum Team members could not agree on the estimate for a story after several rounds. One of them is the Product Owner, who is most aware about the business impact. Another is the senior Developer, who has worked on several similar stories in the past. The third person is a junior Developer, who has to work on the story. Whose estimate should be used during Sprint planning?
Junior Developer
Senior Developer
Product owner
Average of their estimates should be used
Answer explanation
Correct Ans Is Junior Developer————A product owner should not estimate. He or She should clarify – the estimates have to come from the Developers. An senior Developer opinion is valuable and must be considered, but in the event of a disagreement, the estimate of the person who is going to do the actual work should be respected.
9.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
On a Scrum project, a important stakeholder is regularly coming into Developers space taking valuable time and causing distractions. How should this be handled?
The stakeholder should be invited to the Daily Scrum so that he can ask his doubts during the Daily Scrum
The empowered Developers should address the stakeholder by asking him not to come to their area
This should be escalated to the product owner and ask the product owner to deal with the stakeholder immediately.
The Scrum master should take the stakeholder aside and explain the scrum principles to the stakeholder
Answer explanation
The scrum master job is to remove impediments of the Developers. Here the stakeholder is a impediment. So, the stakeholder should be taken to side by the Scrum master or coach and he should be explained that distractions will cause the Developers to digress and Sprint will be affected.
Similar Resources on Quizizz
10 questions
Preventivo vs Adaptativo

Quiz
•
Professional Development
8 questions
Live Session Manajemen Proyek 7

Quiz
•
Professional Development
10 questions
Metologías Ágiles - EduScrum

Quiz
•
Professional Development
10 questions
Waterfall, Agile şi Scrum

Quiz
•
Professional Development
10 questions
Stakeholders in Curriculum Implementation

Quiz
•
Professional Development
10 questions
Web3 Headlines, Heroes, and Hoaxes

Quiz
•
University - Professi...
6 questions
Project Methodology Quiz

Quiz
•
KG - Professional Dev...
10 questions
PSM1-Quiz 8

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade