12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Contingency Reserves are not included in the Project Baseline.
True
False
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Tasks, Work Packages, Contingency Reserves and which option provides the Project Cost Baseline?
Risk Audit
WBS Coding Structure
Control Accounts
Change Control Process
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Management Reserves are included in which option?
Employee Group Bonding Sessions.
The Cost Baseline
To Provide the Work Christmas Party
Project Budget
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Known Unknowns and Unknown Unknowns in respect of Project Risk and Tolerance are mitigated with the provision of which options?
WBS & Project Management Plan
Management Reserves and Change Control Processes
Management and Contingency Reserves
WBS, CBS, OBS Iterations
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The normal payment process means that certain types of costs must be tracked, which option is correct?
committed costs
accruals
actual costs
All options Listed
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Work involved in creating the deliverables and the processes used to create them is called what?
Change Request Elaboration.
Integration Management.
Monitoring and Controlling Process
Project Scope Management.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Product scope is the deliverable where as the Project scope is how you will deliver this using knowledge areas and processes!
True
False
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?