BPM109_Contract Administration_Set4

BPM109_Contract Administration_Set4

University

10 Qs

quiz-placeholder

Similar activities

Transport Quiz 2

Transport Quiz 2

University

12 Qs

Academic vocabulary 1

Academic vocabulary 1

12th Grade - Professional Development

10 Qs

Plumbing level 2 - PP1 - Communication

Plumbing level 2 - PP1 - Communication

University

10 Qs

foreman

foreman

12th Grade - Professional Development

10 Qs

Engagement Series #1 Fun

Engagement Series #1 Fun

KG - University

9 Qs

Week 2 • COMP 2207

Week 2 • COMP 2207

University - Professional Development

15 Qs

Moral Development Quiz

Moral Development Quiz

University

10 Qs

Recruitment, Tenure, Dismissal, and Due Process

Recruitment, Tenure, Dismissal, and Due Process

University

13 Qs

BPM109_Contract Administration_Set4

BPM109_Contract Administration_Set4

Assessment

Quiz

Professional Development

University

Medium

Created by

Alphonsus Ee

Used 9+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Media Image

Which of the following statements is True?

A contract administrator can omit a significant part of the works and award it to another contractor.

A contract administrator must act within his scope of authority.

All variations will entitle the contractor to additional payments.

Omission need not be authentic.

2.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Media Image

A Superintending Officer can issue variation instructions during the defects liability period.

True

False

3.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Media Image

To avoid disputes, all variation works (except emergencies) must be approved by the contract administrator before work commences.

True

False

4.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Media Image

Under the PSSCOC, a Contractor who is given reasonable notice for works to be measured, cannot object to the client's site measurement if he is not present for the site measurement.

True

False

5.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Media Image

Which of the following statements is FALSE?

A contractor who is bound to the main contract can reject variation orders.

The contractor must comply with all variation orders.

Variation payments are paid via payment certificates.

The schedule of rates is usually used in fixed price contracts for valuing variations.

6.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Media Image

Under the PSSCOC, a Contractor must notify the Superintending Officer within ______days from the date of instruction if there is a cost implication.

7

14

21

28

7.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Media Image

Which of the following should be used as the first recourse for the valuation of variations?

Fair market rates

Schedule of rates

Star rates

Daywork rates

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?