Project Controls PC 09 Rev 02
Authored by Gary Carr
Professional Development
1st Grade
Used 9+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Top Down or Bottom Up estimates are as a result of the creation and confirmation of which processes?
Change Requests
Stakeholder Requirements
Risk Analysis
WBS
All options Listed
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A WBS specifically generates the work to be done on the project which can then be scheduled.
True
False
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The CBS specifically assigns monetary values to complete the work generated within the WBS.
True
False
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which Break Down Structure once created and verified allows the project to assign responsibilities?
WBS
CBS
OBS
PBS
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Benchmarking is the term used for what within Projects?
Recognition of Bad Practice.
Recognition of Ignorance in respect of Project Processes.
Recognition of Good Practice.
None of the options listed.
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What does the project term EVM translate to?
Early Variation Management.
Earned Variation Management.
Early Value Management.
Earned Value Management.
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
If Time is shown on a" X axis" and Cost on a "Y axis" what type of graphical line should we see showing the variations against the baselines.
Straight Vertical Line.
Straight Horizontal Line.
Bell Curve.
S Curve.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?