BPM109 Contract Administration_Set1

BPM109 Contract Administration_Set1

University

10 Qs

quiz-placeholder

Similar activities

contract Clauses Quiz

contract Clauses Quiz

University

11 Qs

EE LAWS GROUP 1

EE LAWS GROUP 1

University

10 Qs

Islamic Banking and Finance - 1

Islamic Banking and Finance - 1

University - Professional Development

10 Qs

COMMUNICATIONS

COMMUNICATIONS

University

10 Qs

Advance Payment

Advance Payment

University

8 Qs

Building Laws Quiz 1- PD 1096

Building Laws Quiz 1- PD 1096

KG - Professional Development

15 Qs

IFRS CHALLENGE 2022

IFRS CHALLENGE 2022

University

10 Qs

Next Generation Service Corps Quiz

Next Generation Service Corps Quiz

University

15 Qs

BPM109 Contract Administration_Set1

BPM109 Contract Administration_Set1

Assessment

Quiz

Professional Development

University

Hard

Created by

Alphonsus Ee

Used 13+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

The following are essential ingredients of a valid contract except _________.

counteroffer

offer and acceptance

consideration

intention to create legal relationship

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

The following are factors that vitiates a contract except ___________.

illegal contracts

consideration

misrepresentation

duress

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

Under the PSSCOC, the contractor is issued with _______ when the works are substantially completed.

completion certifcate

certificate of substantial completion

variation order

delay certificate

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

The following are factors to consider when selecting standard forms of contract except the___________.

length of the contract

nature of the contractual relationship intended by the parties

general characteristics of the work

client’s preference

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

Which one of the following tendering methods is suitable for tenders that involve sensitive work installation?

Open tenders

Selective tenders

Limited tenders

Small value purchase

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

Under the SIA contract, when a construction project is completed, the architect is required to issue the _________.

certificate of substantial completion

completion certificate

extension of time certificate

delay certificate

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

When a Superintending Officer orders a Contractor to do additional works, he has to order a/an __________.

direction

instruction

statement

schedule

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?