A project manager is in the middle of executing a project when they discover the project is behind schedule. The project deadline cannot be extended, and the project sponsor will not approve any scope or budget changes. Which of the following is the best course of action for the project manager to take to complete the project faster?
PMP Exam Study Group - Chapter 6 Schedule

Quiz
•
Education
•
KG
•
Hard
quiz eNetwoQ
Used 18+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Hire additional resources and work overtime
Tell the sponsor that the deadline cannot be met
Look at options for fast tracking the critical path
Level the resources
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
To create the project schedule, a project manager needs to break down the project scope and develop a comprehensive list of activities, which are needed to complete the deliverable. What tool or technique should project manager use in this situation?
Work breakdown structure
Decomposition
Progressive elaboration
Gold plating
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
An agile team is using a Kanban board to track their work. There is still quite a bit of work to be done, which was why a new tester was added to the team. The new tester overheard comments from others about too much work in process (WIP) on their Kanban board. Which of the following is considered an example of WIP?
User stories that contain code that is waiting for customer feedback
User stories that have yet to be prioritized by the product owner
User stories that are awaiting selection by the team
Deployed user stories that contain code that has already been integrated
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Following are the activities and durations on a project schedule. The project is in planning. If activities C, D and F are on the critical path, what is the total float for activity D?
4 days
7 days
0 Days
Cannot be determined
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
According to the industry's generally accepted best practices, the electrical work on the appliances assembly line should be completed prior to installing the doors.
What does this sequence of activities represent?
Activity attributes
Discretionary dependencies
Activity list
Mandatory dependencies
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
You have just completed the Develop Schedule process and you are now preparing information for the project sponsor to highlight the activities that may create a delay in the overall project schedule. Which of the following would be most useful in this situation?
Activity attributes
Project network diagrams
Duration estimates
Project calendars
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A project manager had originally planned to use two industrial 3D printers simultaneously for a project but has just learned that one of them will be unavailable. The project manager adjusts the schedule so that the components are created sequentially using one printer. Unfortunately, this action affects the critical path and delays the planned finish date of the project. What tool or technique has the project manager used in this situation?
Fast tracking
Resource smoothing
Crashing
Resource leveling
Create a free account and access millions of resources
Similar Resources on Quizizz
15 questions
Corporate investments and project business

Quiz
•
6th - 8th Grade
10 questions
PMP Exam Preparation Mentoring Ch 4 Integration

Quiz
•
KG
10 questions
PMP Exam Mentoring - Ch 6 Project Schedule Management

Quiz
•
KG
10 questions
Study Group PMP Chapter 4 Project Integration Management

Quiz
•
KG
10 questions
Reviewer

Quiz
•
University
10 questions
PMP Exam Mentoring Ch 8 Project Quality Management

Quiz
•
KG
7 questions
Project Management & Leadership

Quiz
•
University
10 questions
Study Group PMP Exam Preparation Chapter 1, 2 and 3

Quiz
•
KG
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
25 questions
SS Combined Advisory Quiz

Quiz
•
6th - 8th Grade
40 questions
Week 4 Student In Class Practice Set

Quiz
•
9th - 12th Grade
40 questions
SOL: ILE DNA Tech, Gen, Evol 2025

Quiz
•
9th - 12th Grade
20 questions
NC Universities (R2H)

Quiz
•
9th - 12th Grade
15 questions
June Review Quiz

Quiz
•
Professional Development
20 questions
Congruent and Similar Triangles

Quiz
•
8th Grade
25 questions
Triangle Inequalities

Quiz
•
10th - 12th Grade