Chapter 07 Cost Management

Chapter 07 Cost Management

University

20 Qs

quiz-placeholder

Similar activities

Chapter 11 Risk Management

Chapter 11 Risk Management

University

20 Qs

exotic and hyper  cars

exotic and hyper cars

KG - Professional Development

18 Qs

Rip & Run #1 Policy & Mandates in Public Education

Rip & Run #1 Policy & Mandates in Public Education

University

15 Qs

Alternative energy system

Alternative energy system

University

20 Qs

SEVEN ELT AND TEACHER LEADERSHIP

SEVEN ELT AND TEACHER LEADERSHIP

University

20 Qs

Handling Unexpected Expenses

Handling Unexpected Expenses

3rd Grade - Professional Development

20 Qs

Purchasing Management - Gudang Garam

Purchasing Management - Gudang Garam

University - Professional Development

15 Qs

Chapter 04 - Integration Management

Chapter 04 - Integration Management

University

20 Qs

Chapter 07 Cost Management

Chapter 07 Cost Management

Assessment

Quiz

Special Education

University

Hard

Created by

Suci Miranda

Used 32+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following deprecistion methods depreciates the same amount (or percent) each year by dividing the assets cost by the number of years it is expected to be in service?
Straight line
Declining Balance
Sum-of-Years Digits
Units of Time

2.

MULTIPLE CHOICE QUESTION

2 mins • 5 pts

Diana is the project manager for a complex project. Diana suspects that some of her project team members are filling false claims and having false invoices reimbursed. The invoice charges are being charged to the project budget. During which of the following processes can Diana confirm her suspicious regarding her project teams actions?
Validate Scope
Control Scope
Control Costs
Control Schedule

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is not part of Project Cost Management?
Estimating
Budgeting
Controlling
Sequencing

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following statements regarding the Budget at Completion (BAC) and the Estimate at Completin (EAC) is correct for any project?
The BAC is always greater than the EAC
The EAC is always greater than the BAC
he BAC is always equal to the EAC
The BAC is not dependent on the EAC

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the total approved plan for the project work to which the project execution is compared known as?
Earned Value (EV)
Cost Variance
Management Reserves
Performance Measurement Baseline

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

According to the approved plan, Flora should have completed the site inspection, site excavation, lay foundation, and assemble tower tasks. What is the projects current Cost Variance (CV)[Gambar Chapter 7 No 6]
-1200
1200
-7500
7500

7.

MULTIPLE CHOICE QUESTION

2 mins • 5 pts

Crystal is making a presentation on her projects during a board meeting. Although Crystal knows that the project is behind schedule and will be at least a month late, she announces that by the end of her project, her projects total schedule variance will be zero. As the board members do not understand Earned Value Management (EVM) Crystal explains that the schedule variance is calculated by subtracting the projects total planned values from the projects total earned value. What can be concluded from this information?
Crystal is an ethical project manager
Crystal is stating the facts
Crystal is lying
Crystal is trying to deceive the board members

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?