PERT and CPM

PERT and CPM

2nd - 4th Grade

10 Qs

quiz-placeholder

Similar activities

Average Round

Average Round

1st - 12th Grade

10 Qs

DIAGRAMA DE GANT

DIAGRAMA DE GANT

1st - 3rd Grade

6 Qs

School Carnival- Language Power Grds K-2 Lv C

School Carnival- Language Power Grds K-2 Lv C

1st - 2nd Grade

12 Qs

Fake or Fact

Fake or Fact

4th Grade

10 Qs

AMA

AMA

KG - University

6 Qs

Working In Space Vocabulary

Working In Space Vocabulary

2nd Grade

8 Qs

Money Matters to You (Intermediate)

Money Matters to You (Intermediate)

1st - 5th Grade

7 Qs

Rounding money to the nearest dollar

Rounding money to the nearest dollar

1st - 3rd Grade

11 Qs

PERT and CPM

PERT and CPM

Assessment

Quiz

Other

2nd - 4th Grade

Hard

Created by

Dr. Bhat

Used 50+ times

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not a phase of project management?

Project planning

Project scheduling

Project controlling

project being

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A PERT network is activity-oriented while a CPM network is event-oriented

True

false

cant say

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

_________ are used to represent activity in a network diagram.

circle

square

Rectangle

arrow

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The shortest possible time in which an activity can be achieved under ideal circumstances is known as ________

a) Pessimistic time estimate

b) Optimistic time estimate

c) Expected time estimate

d) The most likely time estimate

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to the time estimates made by the PERT planners, the maximum time that would be needed to complete an activity is called as __________

a) The most likely time estimate

b) Optimistic time estimate

c) Pessimistic time estimate

d) Expected time estimate

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The difference between the maximum time available and the actual time needed to perform an activity is known as _________

a) Free float

b) Independent float

c) Total float

d) Slack

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which statistical distribution is assumed by simplified PERT

beta

normal

poisson

binomial

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?