227. The project life cycle is best defined as:
The continuum of a project life cycle.
The phases that a product or service passes through from its start to its completion.
The series of phases that a project passes through from its start to completion.
The various ways requirements and plans are brought from a project charter to completion.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
228. Projects following more of the adaptive side of the project life cycle most closely follow the pattern of:
Sequential, iteration-based phases and continuous overlapping phases.
Sequential, iteration-based phases and sequential nonoverlapping phases.
Continuous overlapping phases and agile-based phases.
Agile-based phases and sequential, iteration-based phases.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
229. All of the following are Process Groups in adaptive environments EXCEPT:
Planning Process Group.
Monitoring and Controlling Process Group.
Scope Management Process Group.
Closing Process Group.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
230. Iterative, agile, and adaptive approaches track, review, and regulate progress and performance by maintaining:
A detailed to-do list
A backlog
A work breakdown structure
Work packages
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
231. _______________ life cycles develop a set of high-level plans for the initial requirements and progressively elaborate requirements to an appropriate level of detail for the planning cycle.
Predictive
Adaptive
Plan-driven
Program
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
232. Project Integration Management includes all of the following EXCEPT:
Prevention is preferred over inspection. It is better to design quality into deliverables, rather than to find quality issues during inspection. The cost of preventing mistakes is generally much less than the cost of correcting mistakes when they are found by inspection or during usage.
Projects and project management are integrative by nature, with most tasks involving more than one Knowledge Area.
The relationships of processes within and between the Project Management Process Groups are iterative.
Managing project performance and changes to the project activities.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
233. Project Scope Management includes all of the following EXCEPT:
Scope can refer to product scope (the features and functions that characterize a product, service, or result), or to project scope (the work performed to deliver a product, service, or result with the specified features and functions).
Projects and project management are integrative by nature, with most tasks involving more than one Knowledge Area
Project life cycles range along a continuum from predictive to adaptive or agile. In a life cycle that uses a predictive approach, the project deliverables are defined at the beginning of the project and any changes to the scope are progressively managed. In an adaptive or agile approach, the deliverables are developed over multiple iterations where a detailed scope is defined and approved for each iteration when it begins.
Completion of the project scope is measured against the project management plan. Completion of the product scope is measured against the product requirements.
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
TRAINING LEAN - CI Palembang

Quiz
•
Professional Development
23 questions
Chapter 5: Digital and Social Media Marketing

Quiz
•
University - Professi...
20 questions
Principles of Event management

Quiz
•
Professional Development
20 questions
Stress management

Quiz
•
Professional Development
20 questions
Google Workspace CE Level 1 Prep

Quiz
•
Professional Development
25 questions
Chap2. Establishing a PPP Framework

Quiz
•
Professional Development
20 questions
Project Management Basics Quiz

Quiz
•
Professional Development
22 questions
Lesson-4 Lead The Project Team

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
15 questions
Core 4 of Customer Service - Student Edition

Quiz
•
6th - 8th Grade
15 questions
What is Bullying?- Bullying Lesson Series 6-12

Lesson
•
11th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade