PMP Stakeholder Management

PMP Stakeholder Management

University

25 Qs

quiz-placeholder

Similar activities

Advanced Project Management Quiz

Advanced Project Management Quiz

University

26 Qs

Project Management

Project Management

University

25 Qs

ניהול פרויקטים

ניהול פרויקטים

University

22 Qs

Exam - Hybrid Project Manager

Exam - Hybrid Project Manager

University

20 Qs

Chapter 3

Chapter 3

University

25 Qs

Software Engineering

Software Engineering

University

20 Qs

Scrum Bootcamp - Level 3

Scrum Bootcamp - Level 3

University

20 Qs

GGSR Midterm Review 10/07/21

GGSR Midterm Review 10/07/21

University

20 Qs

PMP Stakeholder Management

PMP Stakeholder Management

Assessment

Quiz

Other

University

Medium

Used 56+ times

FREE Resource

25 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

What is the purpose of a project charter?
To formally authorize a project or a phase and document initial requirements which satisfy the stakeholder’s needs and expectations.
To document how the project will be planned, executed, monitored/controlled, and closed.
To link the project, which is going to be planned, executed, and
monitored/controlled to the ongoing work of the organization.
To describe the process of performing the work defined in the project management plan in order to achieve the project’s objectives.

2.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

The communications management plan is a document which includes descriptions of:
Project level performance reports
Activity level status reports
Stakeholder communication requirements
Responsibility assignments

3.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

As the project manager, you decided to arrange a team meeting to identify and analyze lessons learned from quality control with stakeholders. What should you do with them?
Document them and make them part of the historical database for the project and the performing organization. 
Discuss them with management and make sure that they remain otherwise confidential.
Publish them in the corporate newsletter. 
Follow your strategic decisions, independent from lessons learned. These decisions have been made and should be implemented whatever the outcomes are.

4.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

As the project manager in a software project which is currently initiated, you want to assess high-level risks. What should you do?
Develop the project charter and a risk management plan to start identifying risks based on those and other documents.
Identify and analyze risk events using qualitative and quantitative techniques.
Develop contingency plans and fallback plans in case the original plan proves wrong.
Discuss the risks documented in your Risk register with the project key stakeholders.

5.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

You have just taken over as manager of a project that will create many benefits for the performing organization, but you sense a high level of resistance in various stakeholders right from the start. What is the most appropriate action to resolve the problem?
Develop a responsibility assignment matrix (RAM) which clearly shows the responsibility of each stakeholder for the various project activities and who needs to be consulted and informed. 
Develop an organization diagram, which places each of the stakeholders at an appropriate position inside the project and allows for certain lines of communication while disallowing others.
Schedule a meeting with these stakeholders to present the project, discuss and establish ground rules, ensure their involvement and identify initial personal and organizational issues.
Do not talk to these stakeholders too much at this time, instead create faits accomplis, which will later force the stakeholders to support the project due to a lack of alternatives for them.

6.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

You are in the process of planning a project and found that stakeholders often have varying objectives and requirements. This makes it hard to come up with a plan with which all objectives will be met. What is probably most helpful to ensure common understanding?
Ask the project stakeholders to build focus groups in order to discuss and remedy conflicting interests.
Create an exhaustive document describing your point of view and ask stakeholders to review it.
Let each stakeholder write a statement of work, merge the documents to a project scope statement.
Use your authorization as the project manager to clearly prioritize the different objectives.

7.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Your management announced that they want to put you on a stretch assignment. In this situation, you should consider that...
...a stretch assignment is going beyond your qualifications right from the start. Whatever your education, knowledge and skills are, you cannot fail personally. Congratulations.
...key stakeholders must have timely and complete information regarding your qualifications to make decisions regarding your suitability for the assignment.
...stretch assignments bear an increased risk of failure, and this is rarely outweighed by the learning and development experience expected to come with the assignment.
...you should avoid the increased hassle coming with the assignment. It will not be enough for you to simply satisfy requirements and achieve objectives. You will have to learn a lot. 

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Other