1.

FLASHCARD QUESTION

Front

Which of the following is NOT a reason for subcontracting?

  • To rely on the subcontractor's knowledge and skills.
  • To outsource the risk to the subcontractor.
  • To lighten the main contractor's workload.
  • To allow the Main Contractor to concentrate his resources on the construction of the building shell.

Back

To lighten the main contractor's workload.

2.

FLASHCARD QUESTION

Front

An ____________ occurs where an original contracting party transfers only contractual rights but not his obligations.

Back

assignment

3.

FLASHCARD QUESTION

Front

The "doctrine of privity" means that a third party can take the contracting parties for court action.

Back

False

4.

FLASHCARD QUESTION

Front

A type of subcontracting that involves a novation process is called _________.

Back

designated subcontracting

5.

FLASHCARD QUESTION

Front

Is a main contractor responsible for the performance of all his subcontractors except designated subcontractors?

Back

False

6.

FLASHCARD QUESTION

Front

The identities of the designated subcontractors are known in the tender document.

Back

True

7.

FLASHCARD QUESTION

Front

Nominated subcontractors are chosen after the main contract is awarded.

Back

True

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Professional Development