MGT1201 Chapter 5: Scope & Work Breakdown Structure

MGT1201 Chapter 5: Scope & Work Breakdown Structure

Assessment

Flashcard

Business

University

Practice Problem

Easy

Created by

Khaiziliyah binti Khalid @ Khalil undefined

Used 2+ times

FREE Resource

Student preview

quiz-placeholder

21 questions

Show all answers

1.

FLASHCARD QUESTION

Front

What is project scope?

Back

Project scope defines what your project will include and deliver, specifying what work needs to be done and what is not included.

2.

FLASHCARD QUESTION

Front

What are the components of the triple constraint in project management?

Back

The triple constraint consists of Scope (what work will be done), Time (how long it will take), and Cost (how much money or resources will be needed).

3.

FLASHCARD QUESTION

Front

What is the purpose of scope management processes?

Back

Scope management processes ensure that no extra work is added without permission, validate the scope with stakeholders, and define what the project will include.

4.

FLASHCARD QUESTION

Front

What is a Work Breakdown Structure (WBS)?

Back

A WBS is a hierarchical decomposition of the total scope of work to accomplish the project objectives and create the deliverables.

5.

FLASHCARD QUESTION

Front

What is the difference between deliverables and milestones?

Back

Deliverables are the actual outputs produced by the project (e.g., reports, systems), while milestones are checkpoints in the project timeline that indicate progress.

6.

FLASHCARD QUESTION

Front

What is a work package?

Back

A work package is a small, manageable piece of work in a project, representing the lowest level in a Work Breakdown Structure (WBS).

7.

FLASHCARD QUESTION

Front

What are estimation techniques in project management?

Back

Estimation techniques are methods used to predict the time, effort, or cost required for tasks or projects, ensuring realistic planning.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?