The video describes a major infrastructure project to connect London with the south-east coast via a high-pressure gas main. The project involves laying a 40-mile pipeline, including a challenging section under the River Medway. The operation is likened to a military mission, with the pipeline being split into parts for easier installation. Once completed, the pipeline will enhance the gas distribution system linking Sussex and East Kent with London.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary goal of the extensive programme mentioned in the video?

To connect London with the southeast coast

To develop a new airport

To build a new railway line

To construct a new highway

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What makes the project under the River Medway particularly ambitious?

It is the most ambitious project of its kind ever undertaken in Britain

It is the first underwater pipeline in Britain

It is the longest pipeline in the world

It uses the largest winch ever built

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is the pipeline section moved towards the river?

By a fleet of trucks

With the help of helicopters

Using a 100-ton winch

By a team of divers

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is the 1,200-ton pipeline section managed for easier handling?

It is airlifted by cranes

It is floated on the river

It is split into four parts

It is transported in one piece

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the expected duration for laying the 2,000 yards of twin pipeline underwater?

One week

Ten days

Two days

Four days