Agile Masterclass: Agile for Project Management - Scrum Event 2: Sprint Planning
Interactive Video
•
Information Technology (IT), Architecture
•
University
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Read more
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the maximum duration allowed for a Sprint Planning meeting?
4 hours
10 hours
6 hours
8 hours
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who is responsible for maintaining the product backlog?
Stakeholders
Development Team
Product Owner
Scrum Master
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the term used to describe the list of items to be completed in a Sprint?
Release Plan
Product Backlog
Sprint Goal
Sprint Backlog
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How does the Development Team decide how to organize the work during a Sprint?
By following a fixed plan
By self-organizing
By consulting the Scrum Master
By using a predefined template
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is one of the key responsibilities of the Scrum Master during Sprint Planning?
To assign tasks to team members
To approve the final product increment
To ensure the meeting stays within the timebox
To decide the Sprint Backlog
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?