What are RAID, CAD, and DCARI?

What are RAID, CAD, and DCARI?

Assessment

Interactive Video

Business

12th Grade - University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial introduces three common project management acronyms: RAID, CAD, and DAKARI. RAID stands for Risks, Assumptions, Issues, and Dependencies, and is the most commonly used. CAD, which includes Constraints, Assumptions, and Dependencies, is considered fundamental but less common. DAKARI, the most comprehensive framework, includes Dependencies, Constraints, Assumptions, Risks, and Issues. The tutorial explains each component, emphasizing the importance of understanding dependencies, constraints, assumptions, risks, and issues in project management. It concludes by suggesting that the choice of framework depends on personal preference and context.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which acronym is considered the most common in project management?

CAD

RAID

DAKARI

None of the above

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the acronym CAD stand for?

Constraints, Assumptions, Dependencies

Constraints, Assumptions, Decisions

Constraints, Actions, Dependencies

Constraints, Actions, Decisions

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which framework is described as the most comprehensive?

RAID

CAD

DAKARI

None of the above

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In project management, what is the primary difference between risks and issues?

Risks are certain, issues are uncertain

Risks are uncertain, issues are certain

Risks are dependencies, issues are assumptions

Risks are assumptions, issues are dependencies

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why are assumptions considered dangerous in project management?

They are not documented

They are always incorrect

They can be forgotten and lead to risks

They are not related to uncertainties