What is the primary purpose of saving a baseline in earned value analysis?
Microsoft Project 2021 From Beginners to Advanced - Example of Earned Value Analysis

Interactive Video
•
Information Technology (IT), Architecture, Social Studies
•
University
•
Hard
Quizizz Content
FREE Resource
Read more
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
To track the number of tasks completed
To compare project progress against a set standard
To ensure all resources are utilized
To calculate the total project cost
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
When should you consider saving a new baseline?
When a project is completed
When a major change occurs in the project
When a task is delayed by a day
When a new team member joins
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the difference between percentage complete and physical percentage complete?
Percentage complete is for resources, while physical percentage complete is for tasks
Percentage complete is automatic, while physical percentage complete requires manual input
Percentage complete is based on cost, while physical percentage complete is based on time
Percentage complete is calculated manually, while physical percentage complete is automatic
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which method should you use if you want the project to calculate earned value automatically?
Physical percentage complete
Resource-based calculation
Manual calculation
Percentage complete
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does a horizontal line in the earned value report charts indicate?
Budget constraints
Future values
Current project status
Past performance
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In an earned value report, what does it mean if the grey and blue lines are above the orange line?
The project is ahead of schedule
The project is on track
The project is not performing well
The project is under budget
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does a negative cost variance (COV) indicate in an earned value report?
The project is on track
The project is ahead of schedule
The project is over budget
The project is under budget
Similar Resources on Quizizz
6 questions
Planning and Control Using Microsoft Project 365 and 2021 - Workshop 17 - Resource Graphs and Tables

Interactive video
•
University
5 questions
PMP Certification Training - Control Cost

Interactive video
•
University
8 questions
PMI-RMP Certification Training - Identifying Risks Input

Interactive video
•
University
3 questions
Planning and Control Using Microsoft Project 365 and 2021 - Workshop 17 - Resource Graphs and Tables

Interactive video
•
University
2 questions
PMI-RMP Certification Training - Perform Quantitative Risk Analysis - Inputs

Interactive video
•
University
2 questions
PMI-RMP Certification Training - Identifying Risks Input

Interactive video
•
University
2 questions
Microsoft Project 2021 From Beginners to Advanced - Earned Value Analysis Basic Terminology

Interactive video
•
University
6 questions
Microsoft Project 2021 From Beginners to Advanced - Beginner's Level Summary

Interactive video
•
University
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
25 questions
SS Combined Advisory Quiz

Quiz
•
6th - 8th Grade
40 questions
Week 4 Student In Class Practice Set

Quiz
•
9th - 12th Grade
40 questions
SOL: ILE DNA Tech, Gen, Evol 2025

Quiz
•
9th - 12th Grade
20 questions
NC Universities (R2H)

Quiz
•
9th - 12th Grade
15 questions
June Review Quiz

Quiz
•
Professional Development
20 questions
Congruent and Similar Triangles

Quiz
•
8th Grade
25 questions
Triangle Inequalities

Quiz
•
10th - 12th Grade