What is Resource Levelling? And how does it differ from Resource Smoothing?
Interactive Video
•
Business, Information Technology (IT), Architecture
•
12th Grade - University
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Read more
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary goal of resource leveling in project management?
To shorten project duration
To reduce project costs
To resolve resource conflicts by fair allocation
To increase the number of resources
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a strategy used in resource leveling?
Reducing project scope
Hiring more managers
Delaying start times of tasks
Increasing project budget
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How does resource smoothing differ from resource leveling?
It increases the number of resources
It shortens project duration
It reduces project costs
It focuses on balancing workload over time
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a key characteristic of resource smoothing?
Increasing project budget
Managing time constraints
Hiring more managers
Reducing project scope
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a disadvantage of using automated algorithms for resource management?
They are always accurate
They require clearly defined skills and tasks
They are cost-effective
They reduce project duration
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
When is manual resource leveling more suitable?
When project costs need to be reduced
For projects with a short duration
When skills and tasks are complex and not easily articulated
For large projects with many resources
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a requirement for using algorithmic resource leveling?
A small number of resources
A short project timeline
A large project budget
Clearly defined skills for each task
Similar Resources on Wayground
6 questions
Microsoft Project 2021 From Beginners to Advanced - Create a Material Resource
Interactive video
•
University
6 questions
gRPC [Java] Master Class: Build Modern API and Microservices - Congrats & Next Steps
Interactive video
•
University
6 questions
Application Development with Swift 2 (Video 6)
Interactive video
•
University
6 questions
HTML CSS and JavaScript for Beginners - A Web Design Course - HTML Form Fieldset
Interactive video
•
University
6 questions
Trump Says US Will 'Take Over' the Gaza Strip
Interactive video
•
University
6 questions
Raspberry Pi and Arduino - Go to The Next Level - Activity 04 - Debug Serial Using LCD Screen
Interactive video
•
University
6 questions
Denmark to build nine artificial islands off the coast of Copenhagen
Interactive video
•
11th Grade - University
2 questions
What is Project Portfolio Management? PM in Under 5
Interactive video
•
12th Grade - University
Popular Resources on Wayground
10 questions
Honoring the Significance of Veterans Day
Interactive video
•
6th - 10th Grade
9 questions
FOREST Community of Caring
Lesson
•
1st - 5th Grade
10 questions
Exploring Veterans Day: Facts and Celebrations for Kids
Interactive video
•
6th - 10th Grade
19 questions
Veterans Day
Quiz
•
5th Grade
14 questions
General Technology Use Quiz
Quiz
•
8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Circuits, Light Energy, and Forces
Quiz
•
5th Grade
19 questions
Thanksgiving Trivia
Quiz
•
6th Grade
Discover more resources for Business
50 questions
International Trade: Reading Comprehension — Grade 12
Quiz
•
12th Grade
5 questions
Banking Basics
Lesson
•
6th - 12th Grade
19 questions
Personal Finance: Credit Reports and Scores
Quiz
•
9th - 12th Grade
23 questions
Ch. 10 Stock Offerings and Investor Monitoring Review
Flashcard
•
12th Grade
17 questions
BizInnovator Startup - Know Your Customer
Quiz
•
9th - 12th Grade