Microsoft Project 2021 From Beginners to Advanced - Set Up Recurring Tasks

Microsoft Project 2021 From Beginners to Advanced - Set Up Recurring Tasks

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains how to set up recurring tasks in project management using a progress meeting as an example. It covers the importance of a consistent pattern for tasks, how to include time elements in scheduling, and how to handle exceptions when meetings fall on non-working days. The tutorial also demonstrates assigning resources to tasks and adjusting task durations.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key requirement for setting up recurring tasks effectively?

Tasks must have a consistent pattern.

Tasks should be scheduled daily.

Tasks must be completed within a week.

Tasks should be assigned to multiple teams.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a potential downside of setting up recurring tasks?

They are only available for daily tasks.

They require a consistent pattern.

They cannot be edited once created.

They automatically assign resources.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can you include time elements in task scheduling?

By using a calendar view.

By setting tasks to repeat weekly.

By changing the date format to include time.

By assigning tasks to different resources.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should you do if a recurring task falls on a non-working day?

Cancel the task.

Reschedule to the next working day.

Ignore the task.

Move the task to the previous day.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens if you change the duration of a recurring task?

The task is deleted.

Only the first task is updated.

All tasks are recreated, including exceptions.

The task is extended by one hour.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can you assign resources to recurring meetings?

By selecting each meeting individually.

By using the Assign Resources option on the project meeting.

By creating a new resource sheet.

By scheduling meetings on different days.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the effect of extending recurring tasks beyond the project end date?

It cancels all future tasks.

It extends the overall project duration.

It has no effect on the project.

It shortens the project duration.