PMI-RMP Certification Training - Escalate and Avoid

PMI-RMP Certification Training - Escalate and Avoid

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Wayground Content

FREE Resource

The video tutorial covers two negative risk strategies: escalation and avoidance. Escalation is used when a threat is beyond the project's scope or resources, transferring the risk to a higher organizational level. Once escalated, the risk is removed from the project's risk register. Risk avoidance involves eliminating the threat or its impact, effectively removing it from the risk register. This strategy may lead to secondary risks. Examples include changing project plans or strategies to avoid risks. The tutorial emphasizes understanding when to use each strategy and the implications for project management.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When is it appropriate to escalate a risk?

When the threat is beyond the project's scope or authority

When the project manager has enough resources

When the risk is within the project scope

When the risk is already mitigated

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens to a risk in the project's risk register once it is escalated?

It is transferred to another project

It is marked as resolved

It is removed from the register

It remains in the register for monitoring

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary goal of risk avoidance?

To reduce the risk's impact to zero

To transfer the risk to another party

To escalate the risk to higher management

To monitor the risk continuously

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is an example of risk avoidance?

Buying insurance for a project

Escalating the risk to a higher level

Taking a train to avoid the risk of a flat tire

Monitoring the risk closely

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For which type of risks is avoidance most appropriate?

Low priority risks with minimal impact

Risks that are outside the project scope

High priority risks with high probability and impact

Risks that have already occurred

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which risk response strategy removes a risk from the risk register?

Transfer

Mitigation

Monitoring

Avoidance

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are some actions that can be taken to avoid risks?

Both A and C

Reducing the project scope

Ignoring the risk

Extending the project schedule