Professional Scrum Master 2 (PSM II) Certification - A Crash Course - Scrum Artifacts

Professional Scrum Master 2 (PSM II) Certification - A Crash Course - Scrum Artifacts

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the roles of product and release backlogs in product development, highlighting how the product owner collaborates with stakeholders and the team to manage these backlogs. It introduces the release burn down chart as a tool for tracking project progress. The tutorial also covers the sprint backlog and sprint burn down chart, emphasizing their importance in monitoring sprint progress. Additionally, it discusses the concept of a releasable product increment and the definition of done. The video concludes by outlining the purpose of various artifacts in product development.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary role of a product owner in managing the product backlog?

To test the final product

To design the user interface

To maintain and prioritize the list of features

To develop the software code

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does a release backlog differ from a product backlog?

It contains all the tasks for the entire project

It is updated daily by the development team

It includes only the features for the next sprint

It is a subset of the product backlog focused on a specific release

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a release burn down chart primarily track?

The number of team members working on the project

The number of bugs in the software

The number of story points and sprints remaining until launch

The total cost of the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of a sprint backlog?

To outline the tasks the development team will work on during a sprint

To list all the features for the entire product

To document the feedback from stakeholders

To track the budget of the project

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a sprint burn down chart, what does the vertical axis typically represent?

The number of team members

The number of completed sprints

The total project budget

The number of tasks remaining