The video tutorial covers the importance and structure of a Sprint review, including the roles of attendees like the scrum team and stakeholders. It emphasizes the definition of done, challenges faced during the Sprint, and solutions. The scrum team demonstrates their work, and the product owner discusses the product backlog and planning. The tutorial also highlights the importance of collaboration, marketplace review, and adherence to timelines and budgets.

Read more

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who are the typical attendees of a Sprint review?

Only the development team

Only the testing team

The scrum team and key stakeholders

The product owner and clients

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the 'definition of done' in a Sprint review?

A list of tasks to be done in the next Sprint

A set of criteria that must be met for a task to be considered complete

A summary of the Sprint's challenges

A checklist of incomplete tasks

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why might a developer choose not to present a user story during a Sprint review?

The story is too complex

The story was completed ahead of schedule

The story does not meet the 'definition of done'

The story is not relevant to the stakeholders

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key focus during the discussion of Sprint challenges?

Listing all the issues without solutions

Discussing how issues were resolved or could be resolved

Avoiding discussion of any issues

Identifying who caused the issues

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What role does the scrum team play in the Sprint review?

They only listen to feedback

They finalize the product backlog

They demonstrate completed work and answer questions

They decide the next Sprint's tasks

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the product owner's responsibility regarding the product backlog?

To ignore it during the Sprint review

To remove completed items without discussion

To discuss its current state and project future targets

To delegate it to the development team

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does the Sprint review influence subsequent Sprint planning?

It only affects the current Sprint

It provides valuable input for planning

It has no influence

It delays the planning process

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?