Critical Path Algorithm Concepts
Interactive Video
•
Computers, Business, Education
•
10th - 12th Grade
•
Practice Problem
•
Hard
Sophia Harris
FREE Resource
Read more
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the first step in Version 1 of the Critical Path Algorithm?
Find the critical path
Remove the task from the diagraph
Create a schedule
Add the first task to the priority list
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After identifying the critical path, what is the next step in the algorithm?
Create a schedule
Find a new critical path
Remove all tasks from the diagraph
Add the first task to the priority list
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
When a task is removed from the diagraph, what is the next action?
Find a new critical path
Mark it as complete
Add it back to the diagraph
Assign it to a processor
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which task is assigned to Processor 1 first?
Task 3
Task 4
Task 2
Task 1
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What happens when Task 2 is completed?
Task 1 becomes ready
Task 4 becomes ready
Task 5 becomes ready
Task 6 becomes ready
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which task is assigned to Processor 2 after Task 1 is complete?
Task 4
Task 7
Task 5
Task 6
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
At what time is Task 9 completed?
21 hours
26 hours
34 hours
31 hours
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
Career Paths and Exploration Insights
Interactive video
•
9th - 12th Grade
11 questions
Rhetoric in Justice Fortis's Argument
Interactive video
•
9th - 12th Grade
11 questions
Financial Planning for 2024
Interactive video
•
9th - 12th Grade
11 questions
Understanding Advertising Strategies
Interactive video
•
9th - 12th Grade
11 questions
Understanding the Evolution and Future of Computing Technology
Interactive video
•
9th - 12th Grade
6 questions
1944: WOLCOTT SPEAKS
Interactive video
•
9th - 12th Grade
6 questions
CLEAN : New advances let doctors tailor medical pr
Interactive video
•
9th - 12th Grade
6 questions
CLEAN : Iraq's Um Qasr port reopens after closing due to protests
Interactive video
•
9th - 12th Grade
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade