PERT Pretest

PERT Pretest

University

10 Qs

quiz-placeholder

Similar activities

Engineering Technician vs Engineer

Engineering Technician vs Engineer

10th Grade - University

10 Qs

Distance, Rate, and Time

Distance, Rate, and Time

10th Grade - University

10 Qs

Ecosystems

Ecosystems

University

10 Qs

GLOBAL SYSTEM FOR MOBILE COMMUNICATION (GSM)

GLOBAL SYSTEM FOR MOBILE COMMUNICATION (GSM)

University

15 Qs

github

github

University

13 Qs

Network Analysis Quiz

Network Analysis Quiz

University

15 Qs

Quiz SMED

Quiz SMED

University

10 Qs

Quiz on Basics of Cyber Hygiene for Higher Education Institution

Quiz on Basics of Cyber Hygiene for Higher Education Institution

University

10 Qs

PERT Pretest

PERT Pretest

Assessment

Quiz

Engineering

University

Practice Problem

Hard

Created by

Ney Froilan

Used 3+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

Graph or bar chart with a bar for each project activity that shows  passage of time which provides visual display of project schedule

PERT/CPM

GANTT CHART

PRIMAVERA

BAR SCHEDULE

2.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

Indicates only precedence relationships and does not require any time of effort

Dummy

Slacks

Float

Event

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Latest time an activity can be completed without delaying critical path time

Early Start

Early Finish

Late Start

Late Finish

4.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

It refers to the amount of extra time that exists for an activity when all activities preceding it start at their Early Start (ES) date.

Float

Slacks

Total Float

Free Float

5.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

The longest path (time) in a network diagram and it determines the project duration.

Critical Activities

Critical Path

Activity on Node

Activity on Arrow

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A perimeter fence required 11,200 units of 6” CHB to complete. If a mason has an average daily installation productivity of 320 units, what is its estimated duration for a crew of 5 mason/day

6 days

7 days

3 days

4 days

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Draw the Network diagram given the ff:

A, B and C are starting activities and may begin at the same time.

 D and E follows A and E is an ending activity

 G follows and depends on C.

 F is dependent on the completion of B and D.

 G and F must be done before H, an ending activity, can start.

What is the Critical Path?

A=5, B=4, C=5, D=3, E=8, F=2, G=6 and H = 5 (all in days)

A-E

A-D-F-H

B-F=H

C-G-H

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?