Integrative Project

Integrative Project

University

7 Qs

quiz-placeholder

Similar activities

Advanced Concepts in Flip-Flops and Counters

Advanced Concepts in Flip-Flops and Counters

University

10 Qs

Introducción a Proyectos

Introducción a Proyectos

University

8 Qs

Engineering Ethics Quiz 2.0

Engineering Ethics Quiz 2.0

University

12 Qs

21ECC404T_PDA_FT 1_Assesment

21ECC404T_PDA_FT 1_Assesment

University

10 Qs

PCS 4: Computer Softwares for Structural Analysis

PCS 4: Computer Softwares for Structural Analysis

University

10 Qs

MAE FYP Report Workshop

MAE FYP Report Workshop

University

10 Qs

Mini Quiz English for Engineer

Mini Quiz English for Engineer

University

12 Qs

Evaluación 2

Evaluación 2

University

9 Qs

Integrative Project

Integrative Project

Assessment

Quiz

Engineering

University

Hard

Created by

Angie Osorio

FREE Resource

7 questions

Show all answers

1.

FILL IN THE BLANK QUESTION

1 min • 1 pt

A project is a temporary endeavor undertaken to create a unique (p)_______

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The correction of a defect in an end item is an example of:

A unique service

A unique product

A unique result

A unique combination of one or more products

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A temporary endeavor in projects refers to:

Projects drive change in organizations

Projects are undertaken at all organizational levels

Indicates that a project has a definite beginning and end

I don't remember

4.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

When does a poject come to an end? (choose two options)

The project’s objectives have been achieved

The objectives will not or cannot be met

The human or physical resources are no longer available

The project is terminated for legal cause or convenience

Developing a new pharmaceutical compound for market

Expanding a tour guide service

I promise to study for the next quiz

5.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Media Image

The desired result of the change driven by the project is described as:

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Refers to the benefit that the results of a specific project provide to its stakeholders.

Project initiation

Current state

Project management

Business value