Project Management Quiz

Project Management Quiz

Professional Development

10 Qs

quiz-placeholder

Similar activities

Trivia

Trivia

Professional Development

14 Qs

Gamification Week 2 - Design Mission and Content

Gamification Week 2 - Design Mission and Content

Professional Development

6 Qs

Project Communications Management

Project Communications Management

Professional Development

15 Qs

Introduction to The DBQ Project Method

Introduction to The DBQ Project Method

KG - Professional Development

10 Qs

Video Conferencing Guidelines and Etiquette

Video Conferencing Guidelines and Etiquette

6th Grade - Professional Development

13 Qs

Project Execution Methodology: Preliminary Contract Activity

Project Execution Methodology: Preliminary Contract Activity

Professional Development

9 Qs

Quiz ACC

Quiz ACC

Professional Development

15 Qs

KL Class Q2

KL Class Q2

Professional Development

10 Qs

Project Management Quiz

Project Management Quiz

Assessment

Quiz

Other

Professional Development

Hard

Created by

Training Pusilkom

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

If SV = -800 and PV = 7000, how much is EV?

6000

8000

6200

9000

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following are the most commonly used performance measures for evaluating whether or not work is being accomplished as planned at any given point of time?

PV & AC

CV & SV

SPI, EV & AC

AC,EV & PV

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

If CPI is 1.03 and AC is $6,000, how much is EV?

200

7000

6180

7200

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

There are 20 stakeholders on a project. What is the total number of potential communication channels in this project?

10

45

190

100

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

You are managing a bridge construction project. Half of the project work has been completed. The total planned cost at this stage was $2.5 million. The actual physical work that has been completed at this stage is worth $2.4 million. You have already spent $5.0 million on the project. What is the Schedule Variance?

$100,000

-$100,000

$2.6 million

$2.5 million

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A task has a pessimistic estimate of 30 days, most likely estimate of 16 days, and optimistic estimate of 10 days. How much is the activity duration based on the PERT technique?

30 days

20 Days

18 Days

10 Days

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Your project is in an early stage and you need to estimate the overall duration. Based on your experience with similar past projects, you estimate a 6-month completion time. What is this type of estimation technique called?

Three point estimating

Bottom-up-estimating

WAG

Analogous

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?