SY53012FP PM Chapter 5

SY53012FP PM Chapter 5

Professional Development

20 Qs

quiz-placeholder

Similar activities

Test for Project Quality Management

Test for Project Quality Management

Professional Development

15 Qs

PM PreCast2 21-35

PM PreCast2 21-35

Professional Development

15 Qs

PMP Integration Management-AC 2019

PMP Integration Management-AC 2019

Professional Development

25 Qs

Maintenance Planning & Application

Maintenance Planning & Application

Professional Development

15 Qs

Maintenance strategy planning & budgeting

Maintenance strategy planning & budgeting

Professional Development

20 Qs

M36_Research (1)

M36_Research (1)

Professional Development

19 Qs

Project Management Bootcamp

Project Management Bootcamp

Professional Development

25 Qs

Magotteaux - Unit 2

Magotteaux - Unit 2

Professional Development

20 Qs

SY53012FP PM Chapter 5

SY53012FP PM Chapter 5

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Phie Lip Wee

FREE Resource

20 questions

Show all answers

1.

OPEN ENDED QUESTION

3 mins • 1 pt

Project Alpha has the following performance data at the end of Month 6.

Planned Value(PV) = $450,000

Earned Value(EV) = $380,000

Actual Cost (AC) = $420,000

Budget at Completion (BAC) = $90,000

Calculate the Schedule Variance (SV).

Evaluate responses using AI:

OFF

2.

OPEN ENDED QUESTION

3 mins • 1 pt

Project Alpha has the following performance data at the end of Month 6.

Planned Value(PV) = $450,000

Earned Value(EV) = $380,000

Actual Cost (AC) = $420,000

Budget at Completion (BAC) = $90,000

Calculate the Cost Variance (CV).

Evaluate responses using AI:

OFF

3.

OPEN ENDED QUESTION

3 mins • 1 pt

Project Alpha has the following performance data at the end of Month 6.

Planned Value(PV) = $450,000

Earned Value(EV) = $380,000

Actual Cost (AC) = $420,000

Budget at Completion (BAC) = $90,000

Calculate the Cost Performance Index (CPI).

Evaluate responses using AI:

OFF

4.

OPEN ENDED QUESTION

3 mins • 1 pt

Project Alpha has the following performance data at the end of Month 6.

Planned Value(PV) = $450,000

Earned Value(EV) = $380,000

Actual Cost (AC) = $420,000

Budget at Completion (BAC) = $90,000

Based on the Cost Performance Index, what can you determine on the budget?

Evaluate responses using AI:

OFF

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary focus during the Project Execution Phase?

Prevent possible problems through careful planning

Keeping the project on track and ensuring activities are properly executed

Defining project scope and requirements

Creating the project charter

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which phase typically consumes the most energy and resources in the project life cycle?

Project Initiation Phase

Project Planning Phase

Project Execution Phase

Project Closing Phase

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does EVM stands for?

Earned Value Mangaement

Earned Value Method

Expected Value Measurement

Executive Value Monitoring

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Professional Development