SY53012FP PM Chapter 5

Quiz
•
Professional Development
•
Professional Development
•
Hard

Phie Lip Wee
FREE Resource
20 questions
Show all answers
1.
OPEN ENDED QUESTION
3 mins • 1 pt
Project Alpha has the following performance data at the end of Month 6.
Planned Value(PV) = $450,000
Earned Value(EV) = $380,000
Actual Cost (AC) = $420,000
Budget at Completion (BAC) = $90,000
Calculate the Schedule Variance (SV).
Evaluate responses using AI:
OFF
2.
OPEN ENDED QUESTION
3 mins • 1 pt
Project Alpha has the following performance data at the end of Month 6.
Planned Value(PV) = $450,000
Earned Value(EV) = $380,000
Actual Cost (AC) = $420,000
Budget at Completion (BAC) = $90,000
Calculate the Cost Variance (CV).
Evaluate responses using AI:
OFF
3.
OPEN ENDED QUESTION
3 mins • 1 pt
Project Alpha has the following performance data at the end of Month 6.
Planned Value(PV) = $450,000
Earned Value(EV) = $380,000
Actual Cost (AC) = $420,000
Budget at Completion (BAC) = $90,000
Calculate the Cost Performance Index (CPI).
Evaluate responses using AI:
OFF
4.
OPEN ENDED QUESTION
3 mins • 1 pt
Project Alpha has the following performance data at the end of Month 6.
Planned Value(PV) = $450,000
Earned Value(EV) = $380,000
Actual Cost (AC) = $420,000
Budget at Completion (BAC) = $90,000
Based on the Cost Performance Index, what can you determine on the budget?
Evaluate responses using AI:
OFF
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary focus during the Project Execution Phase?
Prevent possible problems through careful planning
Keeping the project on track and ensuring activities are properly executed
Defining project scope and requirements
Creating the project charter
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which phase typically consumes the most energy and resources in the project life cycle?
Project Initiation Phase
Project Planning Phase
Project Execution Phase
Project Closing Phase
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does EVM stands for?
Earned Value Mangaement
Earned Value Method
Expected Value Measurement
Executive Value Monitoring
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
Business English 1

Quiz
•
Professional Development
16 questions
Educational Planning

Quiz
•
Professional Development
20 questions
Quiz 1

Quiz
•
Professional Development
20 questions
PMI SP Stakeholder Communications Management

Quiz
•
Professional Development
18 questions
Customer Relations Day 6

Quiz
•
Professional Development
15 questions
RCM Basic Training Quiz

Quiz
•
Professional Development
20 questions
Project Cost Management

Quiz
•
Professional Development
15 questions
Research Proposal Quiz

Quiz
•
Professional Development
Popular Resources on Wayground
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
10 questions
Ice Breaker Trivia: Food from Around the World

Quiz
•
3rd - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
20 questions
ELA Advisory Review

Quiz
•
7th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Multiplication and Division Unknowns

Quiz
•
3rd Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade