Critical Activities Identification Worksheet

Quiz
•
Construction
•
University
•
Hard
hemyza budin
Used 3+ times
FREE Resource
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Based on the tabulated data below, identify the critical activities?
A, B and D.
B, D and F.
C, E and G.
D, E and G.
2.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
Which of the following is categorized as an Activity on Arrow (AOA)?
I. Critical Path Method (CPM).
II. Precedence Diagram Method (PDM).
III. Program Evaluation Review Technique (PERT).
I and II.
I and III.
II and III.
I, II and III.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following statements does NOT represent an advantage of the Precedence Diagram technique?
Precedence diagrams are simple to draw, and easier to read and understand than other systems.
Dummy activities are not compulsory, therefore reducing the number of activities in a network.
The technique is not readily adaptable to both manual and computer programming.
It is easier to expand and modify the network, thus overlapping activities are more easily represented.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In the following Precedence Diagram Method (PDM), B is
Earliest start.
Earliest finish.
Latest start.
Latest finish.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which statement best describes the following Arrow Network Diagram?
B & C follow A; D & E follow C; F follow B & D; G follow E & F.
B & C follow A; D & E follow B; E follows C; F follows D & E.
B & C follow A; D follow B; E & F follow C; G follows D & E & F.
D. B & C follow A; D & E follow B; E follows C; F follows D & E, G follow F.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the fourth stage in Maslow's Hierarchy of Needs?
Physiological Needs.
Self-Actualization.
Esteem.
Love and Belonging.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Free Float (FF) primarily serves the following purposes:
Determine which activities can be delayed without impacting the total float of the preceding activity.
Identify the activities which can be delayed without affecting the total float of succeeding activities.
Establish priorities.
Identify activities that can be delayed without impacting the total float of either the preceding or succeeding activities.
Create a free account and access millions of resources
Similar Resources on Wayground
Popular Resources on Wayground
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
20 questions
PBIS-HGMS

Quiz
•
6th - 8th Grade
10 questions
"LAST STOP ON MARKET STREET" Vocabulary Quiz

Quiz
•
3rd Grade
19 questions
Fractions to Decimals and Decimals to Fractions

Quiz
•
6th Grade
16 questions
Logic and Venn Diagrams

Quiz
•
12th Grade
15 questions
Compare and Order Decimals

Quiz
•
4th - 5th Grade
20 questions
Simplifying Fractions

Quiz
•
6th Grade
20 questions
Multiplication facts 1-12

Quiz
•
2nd - 3rd Grade