Work and Time Problems

Work and Time Problems

Professional Development

24 Qs

quiz-placeholder

Similar activities

General Knowledge quiz

General Knowledge quiz

Professional Development

19 Qs

ASBESTOS: DON’T BE AN EASY TARGET

ASBESTOS: DON’T BE AN EASY TARGET

Professional Development

25 Qs

PWC1010 BUSINESS TENSES & STRUCTURE

PWC1010 BUSINESS TENSES & STRUCTURE

University - Professional Development

24 Qs

HSE 1.4

HSE 1.4

Professional Development

20 Qs

Reassure_Jaipur4

Reassure_Jaipur4

Professional Development

20 Qs

Work and Time Problems

Work and Time Problems

Professional Development

19 Qs

Spongebob quiz

Spongebob quiz

KG - Professional Development

27 Qs

ASSESSMENT (ONLINE QUIZ)

ASSESSMENT (ONLINE QUIZ)

Professional Development

20 Qs

Work and Time Problems

Work and Time Problems

Assessment

Quiz

Education

Professional Development

Hard

Created by

Sethu Ram

Used 1+ times

FREE Resource

24 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Sixteen men can complete a work in 24 days. Twenty four women can complete the same work in 32 days. Sixteen men and sixteen women together worked for twelve days, after which women dropped. How many more men are to be taken to complete the remaining work in 2 days?

32

24

64

48

Answer explanation

Sixteen men can do 1/24 of the work per day, and twenty-four women can do 1/32. Together, they complete 1/12 of the work in 12 days. Remaining work requires 32 more men to finish in 2 days.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A certain number of men can complete a task in 50 days. If there are 5 men more, then it can be finished in 10 days less. How many men are there?

30

10

40

20

Answer explanation

Let the number of men be x. The work done is constant, so x * 50 = (x + 5) * 40. Solving gives x = 20. Thus, there are 20 men.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

2 men and 3 boys can complete a piece of work in 18 days while 3 men and 2 boys can complete the same work in 15 days. In how many days will 4 men and 2 boys complete the work?

16 1119 days

1 119 days

6 1119 days

16 119 days

Answer explanation

Let the work done by 1 man in 1 day be M and by 1 boy be B. From the equations, we find M and B. Substituting these values into the equation for 4 men and 2 boys gives us 16 1119 days to complete the work.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

8 boys and 12 girls together can finish a project work in 5 days. If it takes 50 days for one boy alone to finish the same project, how many days are required for one girl to complete the same project work?

300

150

200

275

Answer explanation

8 boys and 12 girls can complete the work in 5 days, which means their combined work rate is 1/5 of the project per day. One boy's rate is 1/50, so 8 boys' rate is 8/50. Thus, 12 girls' rate is 1/5 - 8/50 = 1/10. Therefore, one girl takes 300 days.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

15 men can complete a task in 30 days. In how many days can 20 men complete that task?

26

22.5

24

28.5

Answer explanation

15 men complete the task in 30 days, totaling 450 man-days. With 20 men, the days required = 450 man-days / 20 men = 22.5 days. Thus, 20 men can complete the task in 22.5 days.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

15 male employees or 20 female employees of a company can complete a project in 26 days. How many days will 30 male employees and 12 female employees together take to complete the project?

8 days

10 days

12 days

14 days

Answer explanation

15 male employees can complete the project in 26 days, which means their work rate is 1/26. Similarly, 20 female employees have the same rate. Thus, 30 males and 12 females can complete it in 10 days.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A man and a woman can complete a work in 8 and 12 days respectively. How many women must assist 2 men to complete the work in 2 days?

3

2

4

5

Answer explanation

A man does 1/8 of the work per day, and a woman does 1/12. Two men do 1/4 of the work per day. To finish in 2 days, they need to complete the whole work, so 3 women (1/4 + 3*(1/12) = 1) are required.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?